1. A change has been requested by the project team to fix a problem by bringing the future
performance of the project in line with the project management plan. Such a change request is
called __.
PMP Exam Prep Quiz
Quiz
•
Specialty
•
Professional Development
•
Medium
EDUARDO CAMPOS
Used 2+ times
FREE Resource
61 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
1. A change has been requested by the project team to fix a problem by bringing the future
performance of the project in line with the project management plan. Such a change request is
called __.
a. Corrective action
Submitted change request
Preventive action
d. Supportive action
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following documents is not used as an input for the scope validation process? Select one:
The requirements traceability matrix, which links requirements to their origin and tracks them throughout the project lifecycle.
The verified deliverables, completed and verified for correctness by the quality control process.
The project management plan, which contains the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.
The responsibility assignment matrix, which describes the responsibilities for correcting the scope in case the client rejects the project deliverables.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Nancy is the Project Manager of an overpass project. The project is 18% complete. The Steering Committee will meet tomorrow. She is looking at the schedule forecasts for all of the following except: Select one:
to find out how much more the project will cost.
to identify any necessary change requests.
to determine if the project is within the defined schedule tolerance ranges.
to find out how much the schedule is delayed.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The expected cost necessary to complete the remaining work for a schedule activity, work breakdown structure component, or the project. This is the description of which of the following terms:
Schedule Performance
Cost Performance Index
c. Estimate to Complete
Estimate at Completion
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The final performance report of a project that was completed 6 months late shows the Cost Performance Index (CPI) as 0.83. What is the Schedule Performance Index (SPI) of this project?
SPI = 1.00
SPI = 0.83
SPI = 0.50
Cannot be determined with the given information
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The results of the Risk Response Planning process include:
Secondary risks, process updates, and risk owners
Contingency plans, project management plan updates, and sensitivity analysis
Risk triggers, contracts, and a risk list
Residual risks, contingency plans, and contingency reserves
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the best method to control changes in the project? Select one:
Make changes quickly when they occur
Direct changes to the change control board (CCB)
Prevent changes from being made
Look for sources of changes
62 questions
Security+ Phase 6
Quiz
•
Professional Development
66 questions
WEEK 2
Quiz
•
Professional Development
63 questions
Aerospace/Drone Review
Quiz
•
10th Grade - Professi...
59 questions
Arkansas License Law / Time Share Law (Quiz 4 of 4)
Quiz
•
Professional Development
61 questions
social aspects of communication
Quiz
•
Professional Development
65 questions
ก.พ.exam
Quiz
•
Professional Development
65 questions
Tin học
Quiz
•
Professional Development
60 questions
final
Quiz
•
Professional Development
25 questions
Equations of Circles
Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)
Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System
Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice
Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers
Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons
Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)
Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review
Quiz
•
10th Grade