Topic 3.2 Project Planning

Topic 3.2 Project Planning

12th Grade

5 Qs

quiz-placeholder

Similar activities

Ch1 the automobile engine

Ch1 the automobile engine

9th - 12th Grade

10 Qs

DBMS Part-1

DBMS Part-1

12th Grade - University

10 Qs

Recap of Sessions 22 & 23

Recap of Sessions 22 & 23

11th Grade - University

10 Qs

CIVILWAR DAY 21 - KWA - (Bearing and Building Regulations)

CIVILWAR DAY 21 - KWA - (Bearing and Building Regulations)

1st Grade - University

10 Qs

Understanding Manual Gearbox Components

Understanding Manual Gearbox Components

11th Grade - University

10 Qs

Levers

Levers

10th Grade - University

10 Qs

Civilwar-Day 32-PWD-Permeability&stresses on soil

Civilwar-Day 32-PWD-Permeability&stresses on soil

9th - 12th Grade

10 Qs

Ignite Your Engine:  A Spark Plug Tune-Up

Ignite Your Engine: A Spark Plug Tune-Up

10th Grade - University

10 Qs

Topic 3.2 Project Planning

Topic 3.2 Project Planning

Assessment

Quiz

Engineering

12th Grade

Practice Problem

Easy

Created by

Nor Saadah

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are the importance of project planning?

I. Acted as a map of the entire project

II. Define the audience and develop a project team

III. Reduce uncertainty element in the project.

I and II

I and III

II and III


I, II and III

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are the importance of Gantt chart?

I. Help to work out the critical path for a project

II. Give a basis for scheduling

III. Allow to plan the allocation of resources needed to complete the project

I and II

I and III


II and III


I, II and III

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Choose the correct definition of Project Planning.

The study of moral issues and decisions confronting individuals and organizations involved in engineering.

  • Organizing project in logical order and Identifying and defining work activities in a manner that help achieve project objectives.

A requirement of our generation to manage the resource base such that the average quality of life that we ensure ourselves can potentially be shared by all future generations

Management approach for an organisation, centered on quality, based on participation of all members and aiming at long term success through customer satisfaction , and benefit to all members of the organisation and society"

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the importance of Gantt Chart?

I  Help to plan out the tasks that need to be completed

II Give a basis for scheduling when these tasks will be carried out

III Allow to plan the allocation of resources needed to complete the project

IV Recognizes and encourages achievement.

I and II

I and III

I, II and III

III and IV

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

5W + 1H tools is a process of selecting logical choice from the available options. 5W + 1H stands for........

What, Who, When, Where, Why and Habit

What, Who, When, Where, Way and How

What, Who, When, Where, Why and How

What, Work, When, Where, Why and How