Quiz n°1B - Risk management plan - Execution
Authored by Willy Freddie Ndjana
Professional Development
Professional Development
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
26 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
According to the Guide, which should be the allocation of expropriation risks?
a. Public
b. Private
c. Shared
d. The PPP Guide does not provide advice on this risk
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The risk related to environmental approvals is generally allocated to the
a. Public Partner
b. Private Partner
c. Shared
d. The PPP Guide does not provide advice on this risk
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which party should assume the consequences of a delay in obtaining permits for construction?
a. Public
b. Private
c. Shared
d. There is no common approach recommended and the Scenario does not provide sufficient information
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Where is the risk of design (basically, errors in the project design) best allocated?
a. Public
b. Private
c. Shared
d. The PPP Guide does not provide advice on this risk
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which party should bear the risk of construction (cost overrun and delay in completion)?
a. Public
b. Private
c. Shared
d. Private but with exceptions as stablished in the contract (e.g. Force Majeure)
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Commissioning risk: the risk of a delay in commissioning due to the state of the works after construction, should be
a. Borne by the Public Partner
b. Borne by the Private Partner
c. Shared
d. This is not a category of risk described in the Guide
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
(About Ground Conditions): what is true with respect to the risk of "adverse geotechnical conditions" related to tunnel excavations
a. It should be allocated to Public party as recommended by the Guide
b. It should be transferred to Private party as any construction risk
c. It should be shared to some extent by the Public as is relevant in this project
d. This risk is irrelevant as per the scenario description and therefore should be assumed by Private party
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?