CP3P - PREPARATION - Risk management plan

CP3P - PREPARATION - Risk management plan

Professional Development

26 Qs

quiz-placeholder

Similar activities

take it easy

take it easy

Professional Development

24 Qs

13 e Commerce

13 e Commerce

KG - Professional Development

21 Qs

Cloud for Sales Quiz 01

Cloud for Sales Quiz 01

Professional Development

21 Qs

PPP Training Georgia

PPP Training Georgia

Professional Development

30 Qs

Chap4. Appraisal

Chap4. Appraisal

Professional Development

24 Qs

Pre & Post Test Hypernet - Employee Induction (NE-2021)

Pre & Post Test Hypernet - Employee Induction (NE-2021)

Professional Development

21 Qs

Security+

Security+

Professional Development

21 Qs

2. Constraints and Challenges

2. Constraints and Challenges

Professional Development

23 Qs

CP3P - PREPARATION - Risk management plan

CP3P - PREPARATION - Risk management plan

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Willy Freddie Ndjana

FREE Resource

26 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

According to the Guide, which should be the allocation of expropriation risks?
a. Public
b. Private
c. Shared
d. The PPP Guide does not provide advice on this risk

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The risk related to environmental approvals is generally allocated to the
a. Public Partner
b. Private Partner
c. Shared
d. The PPP Guide does not provide advice on this risk

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which party should assume the consequences of a delay in obtaining permits for construction?
a. Public
b. Private
c. Shared
d. There is no common approach recommended and the Scenario does not provide sufficient information

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Where is the risk of design (basically, errors in the project design) best allocated?
a. Public
b. Private
c. Shared
d. The PPP Guide does not provide advice on this risk

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which party should bear the risk of construction (cost overrun and delay in completion)?
a. Public
b. Private
c. Shared
d. Private but with exceptions as stablished in the contract (e.g. Force Majeure)

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Commissioning risk: the risk of a delay in commissioning due to the state of the works after construction, should be
a. Borne by the Public Partner
b. Borne by the Private Partner
c. Shared
d. This is not a category of risk described in the Guide

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

(About Ground Conditions): what is true with respect to the risk of "adverse geotechnical conditions" related to tunnel excavations
a. It should be allocated to Public party as recommended by the Guide
b. It should be transferred to Private party as any construction risk
c. It should be shared to some extent by the Public as is relevant in this project
d. This risk is irrelevant as per the scenario description and therefore should be assumed by Private party

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?