which of the sentence is correct ?

Test Quiz 1

Quiz
•
Engineering
•
University
•
Hard
Mandar Mahajan
Used 2+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Estimate gives an idea of cost of the work
Estimate is required to control the expenditure
Estimate decides whether the proposed plan matches the funds available or not
all of the above
Answer explanation
The correct choice is 'all of the above' because each statement is true regarding estimates in the context of cost control and project planning.
2.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Which is not required to Prepare an Estimate ?
Drawings
Specifications
Tender Documents
Rates
Answer explanation
Tender Documents are not required to prepare an estimate. Drawings, Specifications, and Rates are essential components for estimating.
3.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
The quantity has to be measured in Running Meters,
whose length is very small when compared to its width
whose thickness is very small when compared to its length
whose width is very small when compared to its length
None of these.
Answer explanation
The correct answer is 'whose thickness is very small when compared to its length' as running meters are typically measured in terms of length rather than width or thickness.
4.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
All Loading have to be taken in terms of Weight Measurement
False
True
Answer explanation
Loading must be taken in terms of Weight Measurement, therefore the statement is True.
5.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
As a thumb rule, for any item of work whose thickness is greater than _______ the quantity has to be measured in Cubic Measurement
10 mm
150 mm
15 mm
100 mm
Answer explanation
For any item of work whose thickness is greater than 100 mm, the quantity has to be measured in Cubic Measurement. Therefore, the correct choice is 100 mm.
6.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Which is the correct item work considered under square meter unit measurement
Brick work
P.C.C.
R.C.C.
Plastering
Answer explanation
Plastering is the correct item work considered under square meter unit measurement.
7.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
The correct unit measurement for half brick wall is____
Running Meter
Square Meter
Cubic Meter
Kilogram
Answer explanation
The correct unit measurement for a half brick wall is Square Meter because it represents the area covered by the wall, not the length or volume.
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
Manufacturing Processes

Quiz
•
University
10 questions
MWD Technology Quiz

Quiz
•
University
15 questions
Electro 2 PSW 3

Quiz
•
University
15 questions
Simple and Compound Machines

Quiz
•
7th Grade - University
10 questions
Approximate Analysis for Statically Indeterminate Structures

Quiz
•
University
15 questions
Work

Quiz
•
10th Grade - University
11 questions
Quiz: High Voltage Measurement

Quiz
•
University
13 questions
SBL -II Test Quiz 1

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade