Roles of PMO in Organization

Roles of PMO in Organization

4th Grade

5 Qs

quiz-placeholder

Similar activities

Risk Response Strategies - Positive Risks

Risk Response Strategies - Positive Risks

4th Grade

7 Qs

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

Quiz Manejo de Proyectos

Quiz Manejo de Proyectos

1st Grade - University

6 Qs

Make or Buy Decision  (Correction Needed)

Make or Buy Decision (Correction Needed)

4th Grade

7 Qs

PMP 2017 PEOPLE

PMP 2017 PEOPLE

1st - 12th Grade

10 Qs

Management Risiko

Management Risiko

1st - 10th Grade

10 Qs

CARMA

CARMA

1st - 8th Grade

10 Qs

1. PMP Sample Questions

1. PMP Sample Questions

4th Grade

7 Qs

Roles of PMO in Organization

Roles of PMO in Organization

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 7+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to implement a new education system in schools across Nangarhar, the project manager is struggling to find best practices and templates for project planning and execution. As a Supportive PMO, what should the PMO do?

Mandate the use of specific project management tools and techniques

Conduct regular audits to ensure compliance with project management standards

Take over the project planning and execution responsibilities

Provide the project manager with templates, best practices, and training materials

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to build new irrigation systems in agricultural areas of Faryab, the project manager is not following the organization's established project management standards and methodologies. As a Controlling PMO, what should the PMO do?

Monitor the project closely and enforce adherence to the established standards and methodologies

Provide guidance and support without enforcing compliance

Take over the project management responsibilities from the project manager

Allow the project manager to continue without intervention

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project to upgrade the IT infrastructure for a banking institution in Kabul, the organization has decided that all project management responsibilities should be centralized. As a Directive PMO, what should the PMO do?

Take full control of the project management responsibilities, including planning, execution, and monitoring

Support the project manager by providing tools and best practices

Enforce compliance with project management standards while allowing the project manager to make decisions

Provide occasional advice and let the project manager handle the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a humanitarian project to provide relief supplies to earthquake-affected areas in Paktia, the project manager is facing challenges in project documentation and stakeholder communication. As a Supportive PMO, what should the PMO do?

Mandate specific communication protocols and documentation standards

Perform an audit of the project to ensure compliance with communication standards

Take over the stakeholder communication and documentation responsibilities

Provide the project manager with templates for documentation and communication, along with guidance on best practices

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a construction project to build new school buildings in Parwan, the project manager is not adhering to the organization's project management framework. As a Controlling PMO, what should the PMO do?

Allow the project manager to manage the project without interference

Enforce adherence to the project management framework and conduct regular reviews to ensure compliance

Take over the project planning from the project manager

Provide general advice and leave the project manager to decide on implementation