Topic 2 Excavation and Construction Dewatering

Topic 2 Excavation and Construction Dewatering

University

12 Qs

quiz-placeholder

Similar activities

Desain Penyaliran Tambang Kuis 4

Desain Penyaliran Tambang Kuis 4

University

10 Qs

Exploring Uninformed Search Strategies

Exploring Uninformed Search Strategies

University

10 Qs

Momentum and Mass Transfer

Momentum and Mass Transfer

University

15 Qs

Nuclear Safety 8

Nuclear Safety 8

University

10 Qs

Understanding Hydrostatic Equation

Understanding Hydrostatic Equation

University

10 Qs

Understanding Relations in Mathematics

Understanding Relations in Mathematics

University

10 Qs

Quiz 1 - Stability Analysis in Control Systems

Quiz 1 - Stability Analysis in Control Systems

University

10 Qs

Measuring equipment

Measuring equipment

12th Grade - University

7 Qs

Topic 2 Excavation and Construction Dewatering

Topic 2 Excavation and Construction Dewatering

Assessment

Quiz

Engineering

University

Medium

Created by

Norhazirah Imran

Used 3+ times

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To conduct subsurface construction work, the earth has to be excavated and it is important to consider surrounding movements. To hold the ground surface against topple, what is needed to be installed?

ground water

ground mixer

ground support

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For shallow excavation of dry sand and clay for a long-term stability, it can be acceptable to leave certain safe slope to prevent the sides of the ground against topple. The angle of the slope shall be _______.

equal to the angle of friction of the soil

equal to half of the angle of friction of the soil

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

For a large excavation, select one or more reason(s) for it to be infeasible/unsuitable to provide just a safe slope along side wall.

too large span

expensive

consume time

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For ground support installation, which of the following is the general way for sands and silts?

the sheeting is driven up to the excavation level, then lateral bracing is connected as excavation proceeds with depth

the sheeting is driven to a depth below the excavation level, then lateral bracing is connected as excavation proceeds with depth

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For ground support installation, which of the following is the general way for stiff clay and weak rocks?

the sheeting is driven to a depth below the excavation level, then lateral bracing is connected as excavation proceeds with depth

the sheeting is installed in open or partially completed excavation to a depth below the excavation level, then lateral bracing is connected

the sheeting is installed in open or partially completed excavation up to the excavation level, then lateral bracing is connected

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Construction Dewatering means to keep the excavated area ____.

Dry

Wet

Partially Wet/Dry

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Select the dewatering process suitable for shallow excavation and water table up to a depth of 1 m.

Ditches and sumps

Well-points

Vacuum Dewatering

Deep-well Pump

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?