1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following should be carried out before any electrical work takes place?

Safe isolation.

Safe insulation.

Safe continuity.

Safe polarity.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following units should be used to check if a circuit is dead?

Multimeter.

RCD.

Proving.

OHMs.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following tests should be carried out on insulation?

Polarity.

Resistance.

Impedance.

Continuity.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The floor area covered by a ring final circuit must not exceed

25 m²

50 m²

75 m²

100 m²

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The main protection on a domestic consumer unit is provided by which one of the following?

RCD.

RBC.

MCB.

MCD.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A 9.8 kW shower should be protected by a circuit breaker rated at

35 amp

40 amp

45 amp

50 amp

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following tests should be carried out to ensure that phase and neutral are not cross connected?

Polarity

Resistance

Impedance

Continuity

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?