EAC, ETC, and VAC
Quiz
•
Professional Development
•
4th Grade
•
Medium
Afghanistan Center
Used 1+ times
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
In a construction project for building a new school in Kabul, Afghanistan, the initial Budget at Completion (BAC) is $2,000,000. The project is expected to be completed in 12 months. By the end of month 6, the project team has spent $1,200,000 and completed 40% of the work. The planned work completion by this time was 60%. Calculate the Estimate at Completion (EAC), Estimate to Complete (ETC), and Variance at Completion (VAC).
EAC = $2,985,075 ETC = $1,785,075 VAC = -$985,075
EAC = $2,000,000, ETC = $800,000, VAC = $0
EAC = $2,400,000, ETC = $1,200,000, VAC = -$400,000
EAC = $2,000,000, ETC = $1,200,000, VAC = $0
Answer explanation
CPI = EV / AC = ($2,000,000 * 0.40) / $1,200,000 = $800,000 / $1,200,000 = 0.67
Estimate at Completion (EAC) = BAC / CPI = $2,000,000 / 0.67 = $2,985,075
Estimate to Complete (ETC) = EAC - AC = $2,985,075 - $1,200,000 = $1,785,075
Variance at Completion (VAC) = BAC - EAC = $2,000,000 - $2,985,075 = -$985,075
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
During an agricultural project aimed at improving irrigation systems in rural Afghanistan, the BAC is $1,500,000, and the project duration is 10 months. By month 5, the project has spent $900,000 and completed 30% of the work. The planned work completion by this time was 50%. Calculate the EAC, ETC, and VAC.
EAC = $1,875,000, ETC = $975,000, VAC = -$375,000
EAC = $2,000,000, ETC = $1,200,000, VAC = -$500,000
EAC = $1,500,000, ETC = $600,000, VAC = $0
EAC = $3,000,000, ETC = $2,100,000, VAC = -$1,500,000
Answer explanation
Explanation:
CPI = EV / AC = ($1,500,000 * 0.30) / $900,000 = $450,000 / $900,000 = 0.50
Estimate at Completion (EAC) = BAC / CPI = $1,500,000 / 0.50 = $3,000,000
Estimate to Complete (ETC) = EAC - AC = $3,000,000 - $900,000 = $2,100,000
Variance at Completion (VAC) = BAC - EAC = $1,500,000 - $3,000,000 = -$1,500,000
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
In a healthcare project to set up a new clinic in Herat, Afghanistan, the BAC is $1,200,000, and the project is scheduled for 8 months. By the end of month 4, the project team has spent $600,000 and completed 35% of the work. The planned work completion by this time was 50%. Calculate the EAC, ETC, and VAC.
EAC = $1,714,285, ETC = $114,285, VAC = -$514,285
EAC = $1,500,000, ETC = $900,000, VAC = -$300,000
EAC = $1,411,765, ETC = $900,000, VAC = -$211,765
EAC = $1,200,000, ETC = $600,000, VAC = $0
Answer explanation
Explanation:
CPI = EV / AC = ($1,200,000 * 0.35) / $600,000 = $420,000 / $600,000 = 0.70
Estimate at Completion (EAC) = BAC / CPI = $1,200,000 / 0.70 = $1,714,285
Estimate to Complete (ETC) = EAC - AC = $1,714,285 - $600,000 = $1,114,285
Variance at Completion (VAC) = BAC - EAC = $1,200,000 - $1,714,285 = -$514,285
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Given the current status of the construction project for building a new school in Kabul, Afghanistan, where the project is halfway through its timeline (6 months into a 12-month project), the team has spent $1,200,000 and completed 40% of the work, while the planned completion was 60%. The initial Budget at Completion (BAC) is $2,000,000. Calculations show that the Estimate at Completion (EAC) is $2,985,075, Estimate to Complete (ETC) is $1,785,075, and Variance at Completion (VAC) is -$985,075.
Based on this information, what is the right action that the project manager should take?
Reassess the project plan and redistribute resources to accelerate work progress, aiming to meet the original schedule.
Increase the project budget and add additional resources to speed up work and cover the higher expected costs.
Conduct a detailed analysis to identify root causes of cost and schedule deviations, and then implement targeted corrective actions to improve performance indices.
Adjust the project scope and extend the timeline to better align with the current spending and completion rate.
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
During an agricultural project aimed at improving irrigation systems in rural Afghanistan, the Budget at Completion (BAC) is $1,500,000, and the project duration is 10 months. By the end of month 5, the project has spent $900,000 and completed 30% of the work, while the planned completion was 50%. The calculations show that the Estimate at Completion (EAC) is $2,250,000, the Estimate to Complete (ETC) is $1,350,000, and the Variance at Completion (VAC) is -$750,000.
Based on this information, what is the right action that the project manager should take?
Reevaluate the project scope and timeline to ensure alignment with the current spending and completion rate.
Perform a root cause analysis to identify reasons for cost overruns and delays, then implement corrective actions to improve the project's performance indices.
Continue with the current plan as the cost and schedule performance might stabilize over the remaining period.
Allocate additional funds and resources to accelerate work progress and meet the original schedule.
Similar Resources on Wayground
5 questions
Финансовая грамотность
Quiz
•
1st - 5th Grade
9 questions
Mortgage
Quiz
•
1st - 8th Grade
6 questions
EVM Basic Terminology
Quiz
•
4th Grade
10 questions
Uso do FGTS
Quiz
•
4th Grade
10 questions
STG Store Meeting Quiz
Quiz
•
1st - 5th Grade
10 questions
Conocimiento operativo
Quiz
•
1st - 10th Grade
10 questions
Honda Insurance Plus
Quiz
•
1st - 5th Grade
10 questions
Blank Quiz 48
Quiz
•
4th Grade
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade
Discover more resources for Professional Development
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
9 questions
Fact and Opinion
Quiz
•
3rd - 5th Grade
20 questions
place value
Quiz
•
4th Grade
10 questions
Order of Operations No Exponents
Quiz
•
4th - 5th Grade
20 questions
Place Value and Rounding
Quiz
•
4th Grade
12 questions
Text Structures
Quiz
•
4th Grade
15 questions
Subject-Verb Agreement
Quiz
•
4th Grade
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...