
PMI SP Stakeholder Communications Management
Authored by PMI Trainer
Professional Development
Professional Development
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
One of your senior stakeholder in the project complained to you and brought to your notice that the project is not useful for the business unit. What do you do next as a project manager?
Review the business case with your senior stakeholder
Escalate the issue to your manager to keep him notified as stakeholder is not showing interest
Escalate the issue to your sponsor and do not communicate to stakeholder further until issue is sorted out
Escalate the issue to the manager of the senior stakeholder to keep him notified as stakeholder is not showing interest
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is NOT a key consideration when developing a schedule approach?
Project scope and objectives
Available resources and constraints
Organisational culture and structure
Communication plan
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When analyzing major milestones against the Statement of Work (SOW), which of the following should be considered?
Project high level risks and uncertainties
major dependencies in project schedule
high level project constraints
All of the above
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
I cannot finish my day at the job until my colleague comes and starts his shift. which logic is this?
common and basic Simple Finish to Start logic
SS
FF
SF
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Engineer is asking his team members to give the possibilities of the task durations with timelines by considering different use case scenarios. what is he doing?
He is performing Schedule risk analysis
He is collecting inputs for PERT Analysis
He is collecting Best case, worst case and mist likely inputs
All the above
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Critical chain method considers buffers in the schedule
True
False
Never
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the primary purpose of archiving schedule files?
To free up storage space on the project server
To ensure compliance with data protection regulations
To maintain historical records for future reference
To update the project schedule baseline
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?