PMI SP Schedule Monitoring and Controlling

PMI SP Schedule Monitoring and Controlling

Professional Development

15 Qs

quiz-placeholder

Similar activities

Project Controls warm up

Project Controls warm up

Professional Development

12 Qs

15a. PED - Plant Establishment Management

15a. PED - Plant Establishment Management

Professional Development

10 Qs

Project Scheduling

Project Scheduling

Professional Development

15 Qs

PMP PROJECT COMMUNICATIONS MANAGEMENT

PMP PROJECT COMMUNICATIONS MANAGEMENT

Professional Development

10 Qs

Waterfall Mindset1(AKF)

Waterfall Mindset1(AKF)

Professional Development

12 Qs

PMP Team Quiz

PMP Team Quiz

Professional Development

10 Qs

Project Integration Test

Project Integration Test

Professional Development

15 Qs

Project Management Master Class 2

Project Management Master Class 2

Professional Development

12 Qs

PMI SP Schedule Monitoring and Controlling

PMI SP Schedule Monitoring and Controlling

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

PMI Trainer

Used 5+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Can a network diagram have multiple critical paths

Yes

If it has multiple critical paths it means there is incorrect logic

Never possible to have multiple critical paths because scheduling tools will not allow you to do it

Yes, it is recommended to have just to have a backup plan

We need management approval to have multiple critical paths

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Can a project have multiple critical paths?

No

Yes

Yes, but project team need to choose one as critical

No, project team members will not give logic which will lead to multiple paths

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which scheduling technique allows for the optimization of project schedules by iterating through various scenarios?

Critical Chain Method (CCM)

Resource Leveling

Monte Carlo simulation

Precedence Diagramming Method (PDM)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A milestone doesn't have

zero duration

duration

accountability

linkage in schedule

Resources

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a single milestone in project scheduling?

To find out project start and end date

To track progress and performance

To allocate resources and estimate project costs effectively

To identify risks and uncertainties

To find out project end date

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a common quantitative technique used in schedule risk analysis?

Expert judgment

Monte Carlo simulation

Critical Path Method (CPM)

Schedule compression

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a common qualitative technique used in schedule risk analysis?

Risk categorisation

Probability-impact matrix

Delphi technique

Resource levelling

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development