Schedule Management Terms

Authored by Afghanistan Center

Professional Development

4th Grade

Used 9+ times

Schedule Management Terms
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a software development project, the project manager decides that the testing phase can begin two weeks before the development phase is fully completed. What scheduling term describes this overlap?

Lag

Lead

Float

Network Diagram

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the planning of a construction project, the project manager determines that there must be a three-week gap between the completion of the foundation and the start of the framing. Which term describes this intentional delay?

Lead

Network Diagram

Float

Lag

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a marketing campaign project, the project manager uses a visual representation that shows the sequence of project activities and their dependencies. What is this tool called?

Float Chart

Network Diagram

Gantt Chart

PERT Chart

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is planning an IT infrastructure upgrade and identifies that certain tasks must be completed in a specific order due to technical requirements. For example, the servers must be installed before the software can be configured. What type of dependency is this?

Discretionary Dependency

Internal Dependency

External Dependency

Mandatory Dependency

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a product development project, the project manager decides to perform the market analysis and product design simultaneously based on team preferences, although it's not required. What type of dependency is this?

Mandatory Dependency

Discretionary Dependency

External Dependency

Internal Dependency

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a logistics project, the project manager notes that some tasks are dependent on suppliers' deliveries, which are outside the control of the project team. What type of dependency does this describe?

Mandatory Dependency

Discretionary Dependency

External Dependency

Internal Dependency

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project schedule, Task B cannot start until Task A finishes. What type of dependency relationship is this?

Finish to Start (FS)

Start to Finish (SF)

Finish to Finish (FF)

Start to Start (SS)

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?