
Financial Management Quiz
Authored by Amanpreet Kaur
Financial Education
12th Grade

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
42 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A special contract requires 640 units of component T. The inventory of 280 units of component T cost $0.20 per unit but the component is not currently used by the company. The current market price of component T is $0.24 per unit but the inventory could be sold for $0.15 per unit. The relevant cost of the units of component T required for the special contract is:
$100.40
$128.40
$142.40
$153.60
Answer explanation
The relevant cost is calculated as (640 units * $0.24) - (280 units * $0.20) = $153.60 - $56 = $97.60. However, the inventory can be sold for $0.15 per unit, so the net relevant cost is $97.60 + (280 units * $0.15) = $128.40.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements about expected value is NOT correct?
True
False
Answer explanation
The correct answer is False because all statements about expected value are correct.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company's initial budget for month 3 includes sales of $100,000, a contribution to sales (C/S) ratio of 40% and fixed costs of $20,000. If the budgeted sales volume in month 3 is reduced by 5% but contribution per unit, total fixed costs and sales mix are unchanged, which of the following statements, about the change to the budgeted profit or contribution in month 3 is true?
A. The revised budgeted profit would be lower by less than 5%.
B. The revised budgeted profit would be lower by more than 5%.
C. The revised budgeted contribution would be lower by less than 5%.
Answer explanation
The correct choice is A because when the sales volume is reduced by 5%, the profit would decrease by less than 5% due to the fixed costs remaining the same and the contribution per unit unchanged.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following would lead to a favourable variance?
The standard material price was set too low.
The standard material usage was set too low.
Actual labour cost was higher than standard.
Labour hours worked were lower than standard.
Answer explanation
Labour hours worked being lower than standard would lead to a favourable variance as it means less labour cost incurred than expected.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
FGH used to manufacture components that required raw material Q. Currently there are 80 kg of material Q in inventory. The company has no use for the material in the foreseeable future and intends to sell it for scrap. A potential new customer has asked for a price for a large order. This order would require 100 kg of material Q. The company management has decided to quote a price for this work on a relevant cost basis. What would be the relevant cost of Material Q to use in this order?
$230
$198
$110
Answer explanation
The relevant cost of Material Q for the order is the cost of the additional 20 kg needed, which is $198 ($9.90 per kg x 20 kg).
6.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Which THREE of the following are never relevant costs for short-term decision making?
Depreciation costs
Incremental costs
Sunk costs
Variable overhead costs
Committed costs
Answer explanation
Depreciation costs, sunk costs, and committed costs are never relevant for short-term decision making as they cannot be changed or avoided in the short term.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How would the cost of recycling scrap be classified in an environmental costing system?
Environmental internal failure cost
Environmental appraisal cost
Environmental prevention cost
Environmental external failure cost
Answer explanation
The cost of recycling scrap would be classified as an Environmental internal failure cost in an environmental costing system.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?