CM Set No - 2

CM Set No - 2

6th Grade

23 Qs

quiz-placeholder

Similar activities

The Apollo Missions

The Apollo Missions

5th - 12th Grade

20 Qs

Careers Vocabulary Units 1-2

Careers Vocabulary Units 1-2

6th - 8th Grade

20 Qs

PRESERVATION AND CONSERVATION YEAR 6 (SET 7)

PRESERVATION AND CONSERVATION YEAR 6 (SET 7)

6th Grade

25 Qs

Stem Reviewer G6 Q1

Stem Reviewer G6 Q1

6th Grade

22 Qs

LISTENING

LISTENING

1st - 10th Grade

22 Qs

Time Management

Time Management

6th Grade

19 Qs

Tabata Quiz

Tabata Quiz

1st - 12th Grade

20 Qs

Core+ Vocabulary Challenge!

Core+ Vocabulary Challenge!

6th Grade

20 Qs

CM Set No - 2

CM Set No - 2

Assessment

Quiz

Other

6th Grade

Easy

Created by

Sahil Suryawanshi

Used 8+ times

FREE Resource

23 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Activities P, Q, and R instantly follow activity M, and their current starting times are 12, 19, and 10. So, what is the latest finishing time for activity M?

11

10

18

Cannot be determined

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The ratio of current assets to current liabilities is known as

Liquidity ratio

Current ratio

Acid-Test (or Quick) ratio

Debts ratio

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a cash flow series:

Uniform gradient signifies that an income or disbursement changes by the same amount in

each interest period

Either an increase or decrease in the amount of a cash flow is called the gradient

The gradient in the cash flow may be positive or negative

All of these

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

EF = ES + D

LS = LF? D

LF = LS + D

all the above.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an advantage of pert and cpm?

straightforward concept

It does not handle the scheduling of resource allocation

not mathematically complex

Both straightforward concept & not mathematically complex

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The purpose of work break down structure in project planning is mainly to

1. Facilitate and improve the decision making on procurement of resources

2. Relate activities under particular trade specializations to help in organizing for project staff

3. Co-ordinate regarding milestone events across trade specializations to improve the synergy between the trades.

1 and 2 only

1 and 3 only

2 and 3 only

1,2 and 3

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project consists of three parallel paths with durations and variances of (10, 4), (12, 4) and (12, 9) respectively. According to the standard PERT assumptions, the distribution of the project duration is

Beta with mean 10 and standard deviation 2

Beta with mean 12 and standard deviation 2

Normal with mean 10 and standard deviation 3

Normal with mean 12 and standard deviation 3

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?