PJJ PROJECT MANAGEMEN MC

PJJ PROJECT MANAGEMEN MC

Professional Development

5 Qs

quiz-placeholder

Similar activities

EISS

EISS

Professional Development

10 Qs

Week 1 Epidemiology Recap

Week 1 Epidemiology Recap

University - Professional Development

10 Qs

KSSM TINGKATAN 5 SAINS BAB 2.5

KSSM TINGKATAN 5 SAINS BAB 2.5

KG - Professional Development

10 Qs

Sistem Pernafasan kelas 8

Sistem Pernafasan kelas 8

12th Grade - Professional Development

10 Qs

CCT Mind Map

CCT Mind Map

KG - Professional Development

10 Qs

Quality Day 22 Oct 2021

Quality Day 22 Oct 2021

Professional Development

10 Qs

RADIKAL BEBAS, ANTIOKSIDAN DAN PRODUK KESIHATAN

RADIKAL BEBAS, ANTIOKSIDAN DAN PRODUK KESIHATAN

Professional Development

10 Qs

Virtual Experience Sains SMP Pahoa Sesi 1

Virtual Experience Sains SMP Pahoa Sesi 1

KG - Professional Development

10 Qs

PJJ PROJECT MANAGEMEN MC

PJJ PROJECT MANAGEMEN MC

Assessment

Quiz

Science

Professional Development

Practice Problem

Medium

Created by

dokki dipa

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

PERFORM INTEGRATED CHANGE CONTROL TERGOLONG MASUK KE DALAM GROUP PROSES MANA DALAM RANGKAIAN PROSES PROJECT MANAGEMENT

PROJECT PLANNING PROCESS GROUP

SEMUA PROSES DALAM PROJECT KAPAN SAJA

CLOSING PROCESS GROUP

MONITORING & CONTROLLING GROUP

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

KETERKAITAN PROSES CONTROL SCHEDULE SEBAGAI BAGIAN DARI PROSES PERFORM INTEGRATED CONTROL, KECUALI

PENENTUAN PERUBAHAN JADWAL PROYEK

MEMBUAT REGISTER RESIKO PROYEK

STATUS TERKINI DARI JADWAL PROYEK

FAKTOR-FAKTOR DALAM PERUBAHAN PROYEK

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

GAP ANALYSIS DIGUNAKAN PADA EVALUASI PELAKSANAAN PROYEK SBSN MENGADOPSI TOOLS ANALYSIS DARI....

VARIANCE ANALYSIS

WHAT IF ANALYSIS

TREND ANALYSIS

MONTE CARLO ANALYSIS

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

TEKNIK UNTUK MENENTUKAN PENYEBAB (CAUSE) DAN DERAJAT PERBEDAAN ANTARA BASELINE DENGAN KINERJA AKTUAL ADALAH...

TREND ANALYSIS

SENSITIVITY ANALYSIS

VARIANCE ANALYSIS

PESTL

ANALYSIS

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

TOOLS YANG DIGUNAKAN UNTUK CONTROLLING PELAKSANAAN PROYEK DENGAN MANFAAT UNTUK MEMBANDINGKAN PRESENTASE PROGRESS PROYEK DENGAN WAKTU ADALAH...

KURVA LORENZ

KURVA VARIANS

KURVA INDEFEREN

KURVA S