The project team is building high-priority deliverables for the project. In what phase of the project are they performing critical quality assurance activities to ensure the team follows standards and prevents potential defects?

Project management

Quiz
•
Others
•
University
•
Medium
madina kanatkyzy
Used 1+ times
FREE Resource
18 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The planning phase
The closing phase
The monitoring and controlling
The executing phase
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Tomorrow is a big day. The project sponsor has just approved the project, and the project manager is building an agenda for a kick-off meeting. In which of the following phases does the kick-off meeting occur?
The planning phase
The executing phase
The monitoring and controlling phase
The closing phase
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which two documents does the project manager complete during the project initiation phase?
Communications management plan
Stakeholder register
Project charter
Risk register
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which of the following are the two most common lifecycle categories project managers use in project management?
Predictive
Six Sigma
Lean
Adaptive
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A product owner meets with a key customer and determines their requirements. The project manager documents these requirements in the form of user stories. Where will these user stories be held for implementation?
User story backlog
Sprint backlog
Product backlog
Requirements log
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A project manager reviews key documents created in the initiating phase or process group. Which two documents should not be part of this review?
Project management plan
Stakeholder register
Work breakdown structure (WBS)
Project charter
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The sponsor approves the project charter, and planning is underway. Which of the following baselines is the first planning target to complete and gain approval and acceptance of?
Scope baseline
Schedule baseline
Cost baseline
Quality baseline
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Untitled Quiz

Quiz
•
University
15 questions
Business Vocabulary

Quiz
•
University
15 questions
QUIZ IS IT!

Quiz
•
University
15 questions
ITIL Quiz

Quiz
•
University
15 questions
Environmental Impact Assessment Quiz

Quiz
•
University
15 questions
Untitled Quiz

Quiz
•
University
15 questions
vocabulary test 2.1.3

Quiz
•
University
16 questions
Understanding Sports Officiating

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade