001. Pre & Post Test PMP Des 2024

001. Pre & Post Test PMP Des 2024

1st Grade

12 Qs

quiz-placeholder

Similar activities

PMI-SH Manage Project/phase Closure or Transitions

PMI-SH Manage Project/phase Closure or Transitions

1st Grade

15 Qs

Chapt5

Chapt5

1st Grade

10 Qs

Micro Staff Handbook 23-24

Micro Staff Handbook 23-24

1st - 5th Grade

17 Qs

CHAPTER 4 - MONITORING CONTRACT PERFORMANCE

CHAPTER 4 - MONITORING CONTRACT PERFORMANCE

1st - 4th Grade

10 Qs

Checkpoint A - AWS ACF - UNCISAL Turma 1

Checkpoint A - AWS ACF - UNCISAL Turma 1

1st - 3rd Grade

10 Qs

Luscii turns One

Luscii turns One

1st - 6th Grade

11 Qs

AAAS Disaster Relief and Planning

AAAS Disaster Relief and Planning

KG - Professional Development

7 Qs

DFS QUIZ

DFS QUIZ

1st Grade

10 Qs

001. Pre & Post Test PMP Des 2024

001. Pre & Post Test PMP Des 2024

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

sudiyuwono wowo

Used 8+ times

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following approaches encourages plan definition but also acknowledges that once work starts, the priorities may change and the plan needs to be updated to reflect this change?

Waterfall
Kanban
Agile
Scrum

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the below is not of Project Management Talent Triangle?

Technical Project Management

Strategic & Business Management

Leadership

Political & Risk Management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many Process Group, Knowledge Area and Process based on Project Management best practice in PMBOK6?

6 Process Group,

12 Knowledge Area,

49 Process

5 Process Group,

10 Knowledge Area,

49 Process

4 Process Group,

10 Knowledge Area,

50 Process

6 Process Group,

10 Knowledge Area,

49 Process

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. The difference between the late and early start of a task is a:

total time difference
total float or slack time
critical path duration
task buffer time

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Cost of Quality principle includes:

training costs, research costs, development costs, and advertising costs
prevention costs, appraisal costs, internal failure costs, and external failure costs
maintenance costs, production costs, distribution costs, and marketing costs
warranty costs, customer service costs, supply chain costs, and inventory costs

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The agile technique of on-demand scheduling is not suitable when:

the team is experienced and can handle changes efficiently
there is flexibility in the project timeline
there are strict deadlines or dependencies that need to be met
the project scope is well-defined from the beginning

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are working as the project manager on a mega-construction project. You need to prepare a quarterly report for the project investors. You need to collect work performance data and convert that into work performance information. Which of the following processes produces work performance data?

Develop Project Charter
Control Scope
Perform Integrated Change Control

Direct and Manage Project Work

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?