1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

A project manager can defend against scope creep with a good ___________!

Project management plan
Risk management plan
Change control process
Procurement process

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Scope creep results in:

Completion delays, decrease in costs, and increase in project complexity.
On-time deliverables, escalation of costs, and increase in project complexity.
Completion delays, escalation of costs, and decrease in project complexity.
Completion delays, escalation of costs, and increase in project complexity.

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

True or FALSE,: In the context of a project, change is always a bad thing.

FALSE,
True

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Your project team is customer focused and often agrees to incorporate many small scope changes throughout the project execution. The changes are documented in an issues log. Which of the following is not a potential problem?

Management of product specifications and configuration become more difficult.
Many small changes may accumulate to create trouble for one of the project objectives.
Changes with impacts on cost or time will be elevated to the Change Control Board.
Changes may not be integrated across the whole project

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

To ensure control over the incidence and frequency of change, the project manager establishes a:

Work breakdown structure
Responsibility assignment matrix
Work procedure schedule
Change control process

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The purpose of capturing lessons learned is:

To document who performed well on the project and who did not so that poor performers can be punished.
To show stakeholders how difficult the project was so that next time their demands will not be so high.
To capture what went well so that you can recreate the good and to capture what could have gone better so that next time it will go better.
To show that you are following project management best practices and therefore you are a superior project manager.

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

A good change process will:

Be very complex in order to discourage changes.
Have change thresholds that are appropriate for the type of change.
Allow the project manager to approve all changes.
Require the same level of approval for all changes.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for World Languages