RM Review Training Preparation

Quiz
•
Business
•
9th Grade
•
Easy
Bobbie Jones
Used 2+ times
FREE Resource
16 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which document serves as the official authorization for a project?
WBS
Statement of Work
Project Scope
Project Charter
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If a house remodel project is underway and the builder realizes the doors and windows are no longer going to arrive on time but he can get them for 20% more than scope agreement from another vendor. what should the project manager do FIRST to resolve this problem?
Consult with the customer to reach a possible solution.
Accept the increase in price and price the cost onto the customer.
Pause the project.
Accept the delay in scope.
3.
MATCH QUESTION
1 min • 1 pt
Match the task to the stakeholder most likely responsible to complete it.
Customer
Report the completion of deliverables to the project manager
Sponsor
Updates key stakeholders on project phase compmletions
Team Member
Initially report the tasks as complete
Managers
Ultimately determines the quality as acceptable
Project Manager
Adds the most value to a project
4.
MATCH QUESTION
1 min • 1 pt
Match the definition to the phrase that best represents it.
Prevent Future errors; fix defects
Quality Assurance
Specific goals.
Project Purpose
The end goal.
Milestone
Defect prevention; method to measure Q.
Objective
Significant events.
Quality Control
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a slipped task?
A task that is in progress and behind schedule
A task that is changed to being done concurrently with other tasks instead of sequentially
A task completed behind schedule
A task that needs additional resources to be completed in less time
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a slipping task?
A task that is in progress and behind schedule
A task that is changed to being done concurrently with other tasks instead of sequentially
A task completed behind schedule
A task that needs additional resources to be completed in less time
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is crashing?
A task that is in progress and behind schedule
A task that is changed to being done concurrently with other tasks instead of sequentially
A task completed behind schedule
A task that needs additional resources to be completed in less time
Create a free account and access millions of resources
Similar Resources on Wayground
15 questions
NV CTE Standard 10.0 Understanding Management's Role

Quiz
•
9th Grade
15 questions
Marketing Quiz

Quiz
•
9th Grade
15 questions
5.01 Pre-Employment Quiz

Quiz
•
9th - 12th Grade
21 questions
PM2 Unit 4 Review (PMI)

Quiz
•
9th - 12th Grade
18 questions
Feasibility Studies

Quiz
•
9th - 12th Grade
20 questions
ESB Vocabulary Quiz 2

Quiz
•
9th - 12th Grade
13 questions
Chapter 6 Quiz #1

Quiz
•
9th Grade - University
20 questions
Rules to Live By

Quiz
•
9th - 12th Grade
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade