Fundamentals of Project Mngmt 2: planning stage

Fundamentals of Project Mngmt 2: planning stage

University

9 Qs

quiz-placeholder

Similar activities

REPRESENTACIÓN DE PROYECTOS MEDIANTE UNA RED

REPRESENTACIÓN DE PROYECTOS MEDIANTE UNA RED

University

10 Qs

Part 3 - DSN new

Part 3 - DSN new

University

10 Qs

Día 1 Semana calidad 2021: PTS Calidad en la fuente

Día 1 Semana calidad 2021: PTS Calidad en la fuente

1st Grade - University

10 Qs

Gestão de Projetos - 1. Início

Gestão de Projetos - 1. Início

University

9 Qs

ISO 9001:2015 101

ISO 9001:2015 101

University

10 Qs

EdPsych Piaget Review

EdPsych Piaget Review

University

13 Qs

Tuckman's Team Development Lifecycle

Tuckman's Team Development Lifecycle

University

8 Qs

CAIIB QUIZ 1

CAIIB QUIZ 1

University

10 Qs

Fundamentals of Project Mngmt 2: planning stage

Fundamentals of Project Mngmt 2: planning stage

Assessment

Quiz

Professional Development

University

Medium

Created by

Maxime Bourdillon

Used 3+ times

FREE Resource

9 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

30 sec • 1 pt

What is the name of the second stage of a project life cycle?

2.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

The hierarchical decomposition of the total scope of work in tasks is called the "Work _________ Structure"

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The tool with the Earliest Start/End Date, the Latest Start/End Date and the Margin is named

WBS

PERT network

GANTT chart

RACI

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The tool to visualise the entire project planning and manage project progress is

The Work Breakdown Structure

The RACI Matrix

The PERT network (Program Evaluation & Review Technic)

The Gantt chart

5.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

The chart describing the participation of various roles in completing tasks or deliverables is called the "Responsability ___________ matrix"

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

How do we call the method to analyse risks?

RACI

YOLO

PERT

FMEA

7.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

How do we call the part in which we identify subteams, meetings objectives and frequency, documents, committees, communication flows?

8.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The Go/No Go is decided at the end of

Initiating stage

Planning stage

Realization stage

Closure stage

A shifumi between sales department and accounting team

9.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The Kick-off Meeting is held at the end of :

Initiating stage

Planning stage

Realization stage

Closure stage