Fundamentals of Project Mngmt 2: planning stage

Fundamentals of Project Mngmt 2: planning stage

University

9 Qs

quiz-placeholder

Similar activities

Planificación del tiempo - PMI

Planificación del tiempo - PMI

University

7 Qs

Admón. Proy-EXAMEN-T3-1a OP

Admón. Proy-EXAMEN-T3-1a OP

University

12 Qs

Actividades de Diagrama y Tabla de Secuencia de Actividades

Actividades de Diagrama y Tabla de Secuencia de Actividades

University

7 Qs

Unidad 1. Introducción a la gestión de proyectos

Unidad 1. Introducción a la gestión de proyectos

University

10 Qs

implementacion 1 semana 3

implementacion 1 semana 3

University

10 Qs

Adm Oper 10

Adm Oper 10

University

10 Qs

Fundamentals of Project Mngmt 2 : realization and closure stage

Fundamentals of Project Mngmt 2 : realization and closure stage

University

6 Qs

Fundamentals of Project Mngmt 2: planning stage

Fundamentals of Project Mngmt 2: planning stage

Assessment

Quiz

Professional Development

University

Medium

Created by

Maxime Bourdillon

Used 3+ times

FREE Resource

9 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

30 sec • 1 pt

What is the name of the second stage of a project life cycle?

2.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

The hierarchical decomposition of the total scope of work in tasks is called the "Work _________ Structure"

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The tool with the Earliest Start/End Date, the Latest Start/End Date and the Margin is named

WBS

PERT network

GANTT chart

RACI

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The tool to visualise the entire project planning and manage project progress is

The Work Breakdown Structure

The RACI Matrix

The PERT network (Program Evaluation & Review Technic)

The Gantt chart

5.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

The chart describing the participation of various roles in completing tasks or deliverables is called the "Responsability ___________ matrix"

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

How do we call the method to analyse risks?

RACI

YOLO

PERT

FMEA

7.

FILL IN THE BLANK QUESTION

45 sec • 1 pt

How do we call the part in which we identify subteams, meetings objectives and frequency, documents, committees, communication flows?

8.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The Go/No Go is decided at the end of

Initiating stage

Planning stage

Realization stage

Closure stage

A shifumi between sales department and accounting team

9.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The Kick-off Meeting is held at the end of :

Initiating stage

Planning stage

Realization stage

Closure stage