All-in-one CAPM/PMP: Chapter 5 - Scope
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Medium
Patrick Pepin
Used 3+ times
FREE Resource
Enhance your content in a minute
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Henry is the project manager for his organization, and management has asked him to create a project management plan to define the scope statement.
Which project management plan guides the creation of the detailed project scope statement?
The charter
The project management plan
The project scope plan
The project scope management plan
Answer explanation
The project scope management plan defines the creation of the detailed project scope statement. A, the charter, does include the preliminary project scope statement, but not the detailed one defined by the project scope management plan. B, the project management plan, is a parent of the project scope management plan. C is not a valid plan, so this answer is incorrect.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager of the GYH Project. This project will create a walking bridge across the Tennessee River. You've been asked to start the process of creating the project scope statement and you need to gather the elements for this process.
Which one of the following is not needed to define the project scope?
A project charter
Organizational process assets
A risk management plan
Requirements documentation
Answer explanation
At this point, you won't need, or likely have, the risk management plan to define the project scope. A, B, and D are incorrect statements because you'll need the project charter, organizational process assets, and the requirements documentation to define the project scope.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager of the BHY Project. Your project customer has demanded that the project be completed by December 1.
December 1 is an example of which one of the following?
A constraint
An assumption
A project boundary
Product acceptance criteria
Answer explanation
This is an example of a project constraint. B is incorrect because this is a requirement, not an assumption. C is incorrect because project boundaries define things that are within and outside of the project scope. D is incorrect because product acceptance criteria are an example of functions and features the product must have to be acceptable to the customer.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Marty is the project manager of the Highway 41 Bridge Project and he's working with his project team members to create the WBS. Marty shows the team how to break down the project scope into the WBS components, but the team doesn't understand how far down the breakdown should occur.
Marty should call the lowest-level item in a WBS what?
A deliverable
A work package
An activity
A leaf object
Answer explanation
The smallest item in the WBS is called the work package. A, deliverables, may be true to a degree, but B is a more precise answer. C is incorrect because activities are found in the activity list. D is an invalid WBS term
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are working with the project team to create the WBS. Some elements in the WBS can't be broken down yet. You and the team elect to break down these items later in the project as more details become available.
This approach to creating the WBS is also known as what?
Decomposition
The 8/80 Rule
Parkinson's Law
Rolling wave planning
Answer explanation
I his is a clear example of rolling wave planning. A is incorrect because decomposition describes the breakdown process of the project scope. B is incorrect because the 8/80 Rule defines the guideline for the amount of labor that should be related to each work package in the WBS. C, Parkinson's Law, is not relevant to this question. Parkinson's Law states that work will expand to fulfill the amount of time allotted to it.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager for your organization and you're creating the WBS for a new project. In your WBS, you're numbering each level of the components following a project sequenced numbering order. lour WBS is numbered in a hierarchical fashion for easy identification and reference.
This numbering scheme is called what?
Code of accounts
Chart of accounts
WBS template
WBS dictionary
Answer explanation
The WBS numbering scheme is called the code of accounts. B, chart of accounts, is a project management accounting system. C, a WBS template, can be a prepopulated WBS or a WBS from a previous project used to define the current project's WBS. D is incorrect because the WBS dictionary defines the attributes of each WBS element.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You'll use the scope management plan to define the project scope statement. You'll also use this plan to build the scope baseline.
Which two items are parts of the scope baseline for the project?
The project scope management plan and project charter
The project scope management plan and the WBS
The WBS and WBS dictionary
Time and cost baselines
Answer explanation
The WBS and WBS dictionary are two of the three components of the scope baseline. The approved detailed project scope statement is the third portion of the scope baseline. A, B, and D are all incorrect because they do not accurately define the scope baseline.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
15 questions
REVISED CODE OF CONDUCT QUIZ BEE
Quiz
•
Professional Development
20 questions
7290-602 Knowledge of Isolation & Re-energising HV systems
Quiz
•
Professional Development
20 questions
Negotiable Instruments
Quiz
•
Professional Development
15 questions
Latihan Soal PKP Bagian 1
Quiz
•
Professional Development
15 questions
PELAYANAN PUBLIK LATSAR CPNS BULUKUMBA
Quiz
•
Professional Development
18 questions
Waste
Quiz
•
Professional Development
15 questions
Universal Design for Learning
Quiz
•
Professional Development
18 questions
Infallible Vedas (DYS 2)
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade