1.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

The collection of generally sequential and sometimes overlapping project phases differentiated by a distinct work focus is known as what?

Project management information system

Project management methodology

Project management office

Project life cycle

2.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

All of the following are basic characteristics of the project life cycle except?

Closing the project

Checking the project work

Starting the project

Carrying out the project work

3.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Sayed is looking at his project budget and notices that the cost and staffing levels are high. At which point in the project would this generally be?

Starting the project

Organizing and preparing

Carrying out the work

Closing the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

What is the name of the document that lists any problems that stakeholders may have and records what is being done about them?

. Change log

Issue log

Stakeholder register

Stakeholder management plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Sumith and his project team are currently breaking down all the project deliverables into the smallest useful units so that they can then estimate costs for each of these units and then aggregate these estimates into a total project cost estimate. What is the name of the technique that Sumith and his team are using to estimate costs?

Parametric estimatin

Bottom-up estimating

Low-level estimating

Project management software

6.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

While developing individual cost estimates for work packages on his project, Varun uses a technique that requires him to use a statistical relationship between historical data and other variables to calculate a cost estimate for a schedule activity resource. What is this estimating technique more commonly referred to as?

Statistical estimating

Bottom-up estimating

Parametric estimating

Top-down estimating

7.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Marissa’s project sponsor has asked her to provide a cost estimate quickly to give the project steering group an idea of what the costs for a particular work package will be. Which of the following estimating techniques would Marissa choose to use?

Analogous estimating

Parametric estimating

Resource rate estimating

Bottom-up estimatin

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?