Critical Path Method Quiz

Critical Path Method Quiz

University

12 Qs

quiz-placeholder

Similar activities

IB Business Management - BMT - Gantt Charts Quiz

IB Business Management - BMT - Gantt Charts Quiz

9th Grade - University

13 Qs

Management and Organizational Structure Quiz

Management and Organizational Structure Quiz

University

15 Qs

Startup Buzz- Demo

Startup Buzz- Demo

University

14 Qs

Scrum 101: The Introduction

Scrum 101: The Introduction

University

10 Qs

Midterm Exam in Introduction to Project Management

Midterm Exam in Introduction to Project Management

University

15 Qs

Business Ethics : Moral Reasoning Quiz 1

Business Ethics : Moral Reasoning Quiz 1

University

12 Qs

RIsk Management

RIsk Management

University

10 Qs

Critical Path Method Quiz

Critical Path Method Quiz

Assessment

Quiz

Business

University

Hard

Created by

Dr. Bekal

Used 3+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the Critical Path Method (CPM) used for?

Calculating total project costs

Measuring progress against plans

Managing day-to-day operations in all departments

Analyzing, planning, and scheduling large, complex projects

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an essential characteristic for analysis by CPM?

Jobs that must be performed in technological sequence

Continuous-flow process activities

Jobs that cannot be started and stopped independently

Jobs that do not have a well-defined collection

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical path in a project?

The path with the most number of jobs in a project

The shortest path in time from Start to Finish

The longest path in time from Start to Finish

The path with the least number of jobs

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of finding ways to shorten jobs along the critical path?

To shift the critical path to include more jobs

To reduce the over-all project time

To increase the total project time

To reduce the time required to perform noncritical jobs

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of total slack in the Critical Path Method?

It indicates the minimum time necessary to complete the entire project

It is the amount a job can be delayed without delaying the early start of any other job

It is the difference between a job’s early start and its late start

It represents the maximum amount of time a job can be delayed without delaying the project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of using CPM for decision making?

It provides a simple and direct way to display the interrelations in a project

It eliminates the necessity of careful time studies for all jobs

It enables the manager to quickly study the effects of 'crash' programs

It focuses attention on the small subset of jobs that are critical to project completion time

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the SPAR program in CPM?

To determine the critical path in a project

To identify the jobs with positive free slack

To schedule projects having limited resources

To calculate the cost of carrying out a project

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?