24-25 PMR Unit 1 - PM2 Adaptive, Predictive, Hybrid follow up

24-25 PMR Unit 1 - PM2 Adaptive, Predictive, Hybrid follow up

10th Grade

10 Qs

quiz-placeholder

Similar activities

J277 Operating Systems

J277 Operating Systems

10th - 12th Grade

15 Qs

R081 - Planning

R081 - Planning

9th - 11th Grade

9 Qs

Adobe Premiere Pro

Adobe Premiere Pro

10th - 12th Grade

10 Qs

1.5 System software - revision quiz

1.5 System software - revision quiz

10th - 11th Grade

15 Qs

BIM1014 Quiz4

BIM1014 Quiz4

KG - University

10 Qs

BTEC DIT C1 LAB - Project Planning Basics

BTEC DIT C1 LAB - Project Planning Basics

10th Grade

10 Qs

Internet of Things

Internet of Things

9th - 10th Grade

10 Qs

Project Life Cycle

Project Life Cycle

10th Grade

8 Qs

24-25 PMR Unit 1 - PM2 Adaptive, Predictive, Hybrid follow up

24-25 PMR Unit 1 - PM2 Adaptive, Predictive, Hybrid follow up

Assessment

Quiz

Computers

10th Grade

Easy

Created by

Bobbie Jones

Used 6+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MATCH QUESTION

1 min • 1 pt

Match the key words or descriptions to the type of project management it would most likely need for projects.

Adaptive

Retail Business

Predictive

Strict Regulations

Hybrid

Software Design

2.

MATCH QUESTION

1 min • 1 pt

Match the key words or descriptions to the type of project management it would most likely need for projects.

Predictive

Completely defined Scope

Hybrid

Customization ex. A Science Lab

Adaptive

Work is well defined timing is not set

3.

MATCH QUESTION

1 min • 1 pt

Match the project to the type of management best to fit its needs.

Predictive

Building constructed to scope

Hybrid

A bank App that offers customization

Adaptive

Planting a Flower Garden

4.

MATCH QUESTION

1 min • 1 pt

Match the key words or descriptions to the type of project management it would most likely need for projects.

Hybrid

Automotive Industry

Adaptive

Government Agency

Predictive

Startup Prototyping

5.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Choose 2 characteristics or tools used in the adaptive approach of PM.

Changing Fast

Set List of Deliverables

Uses Product Backlog

Scope Creep Common

Answer explanation

In Adaptive you really do not detail a scope and your deliverables are not set they change!

Agile does look at the kanban board for product backlog and handle rapidly changing projects.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of project management would probably be used to build a bank and their E-Commerce platforms.

Adaptive

Predictive

Hybrid

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of project management would probably be used to make custom products for the local farmer over a period of time.

Adaptive

Predictive

Hybrid

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?