Project Management Quiz

Project Management Quiz

University

7 Qs

quiz-placeholder

Similar activities

OPERATIONAL MODELS

OPERATIONAL MODELS

University

5 Qs

structural

structural

University

4 Qs

Tunnel design philosophy

Tunnel design philosophy

University

10 Qs

Design process

Design process

4th Grade - Professional Development

6 Qs

Quiz: Hoard et al. 2019

Quiz: Hoard et al. 2019

University

5 Qs

Building Technology 1 of 22

Building Technology 1 of 22

KG - Professional Development

12 Qs

Verizon - UXINDIA Stall Quiz 2

Verizon - UXINDIA Stall Quiz 2

University - Professional Development

10 Qs

What is 3D animation?

What is 3D animation?

University

6 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Design

University

Hard

Created by

Drielly Fernandes

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the next step after finishing the project scope?

Estimate resources

Define activities

Sequence activities

Develop schedule

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the main purpose of developing a project schedule?

To communicate project results to stakeholders

To create a detailed plan for project execution

To track project progress and performance

To allocate resources to project activities

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of developing a diagram of precedence?

To illustrate activity sequences and interdependencies

To define activities

To estimate resources

To sequence activities

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the rule for developing the network diagram?

The network must be flexible with no specific rules

Each activity must have a unique identification number

Loops and conditionals are allowed

The flow of the network is from right to left

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of identifying the critical path in a project schedule?

To identify activities with slack

To identify activities with leads

To determine the maximum time required to complete the project

To analyze the impact of variations in activities

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the main reason for reducing the duration of a project?

To reduce the project budget

To meet the project deadline

To increase the scope of the project

To improve the quality of the project

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the technique used to reduce the project duration without changing the scope?

Resource leveling

PERT analysis

Fast tracking

Critical path method