CH. 2 - Project Charter, Roles, Requirement Gathering CH2

CH. 2 - Project Charter, Roles, Requirement Gathering CH2

12th Grade

45 Qs

quiz-placeholder

Similar activities

LW Revised Final Review PM1

LW Revised Final Review PM1

9th - 12th Grade

40 Qs

Leadership & Management(Stakeholders)

Leadership & Management(Stakeholders)

12th Grade

45 Qs

PMI: Leadership & Communication

PMI: Leadership & Communication

9th - 12th Grade

40 Qs

Pm 2 Week 1

Pm 2 Week 1

12th Grade

40 Qs

US Banking System (B2)

US Banking System (B2)

9th - 12th Grade

40 Qs

Conflict Management

Conflict Management

12th Grade - University

40 Qs

BM 1 Unit 1 Review

BM 1 Unit 1 Review

12th Grade

47 Qs

CH. 2 - Project Charter, Roles, Requirement Gathering CH2

CH. 2 - Project Charter, Roles, Requirement Gathering CH2

Assessment

Quiz

Business

12th Grade

Medium

Created by

Migdalyn Vega

Used 4+ times

FREE Resource

45 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a Project Charter?

It is a detailed project plan with timelines and milestones.

It is a formal document that serves as the official authorization and existence of a project.

It is an informal agreement between project team members.

It is a contract between the project sponsor and the client.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for creating a Project Charter?

The Project Sponsor

The Project Manager

The Client

The Team Members

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a Project Charter enable the Project Manager to do?

Terminate the project

Begin allocating resources to project activities

Change the project scope without approval

Increase the project budget arbitrarily

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a function of a Project Charter?

Roadmap for the project

Provides a framework for the team to follow

Clear understanding of the goals and expectations

Detailed risk assessment for each phase of the project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the project charter serve as?

A formal agreement between all parties involved in the project

A casual understanding between team members

A legal document for external stakeholders

A performance report for the project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the project charter detail?

The project's social media strategy

The scope, deliverables, timelines, budget, and other important factors

The personal information of the project team

The marketing plan for the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When is the Project Charter typically created?

At the end of a project

After the project's first milestone

At the beginning of a project

During the project closure phase

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?