1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

  • 300

  • 50

  • 600

  • 25

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

  • -$48,654

  • 13 percent

  • -$225,000

  • 0.98

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

  • Static

  • Deterrent

  • Noise

  • Barrier

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

  • Scope of statement

  • Project charter

  • Statement of work (SOW)

  • WBS

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that
Fred needs to report to management?

  • $122,845

  • -$51,000

  • -$85,000

  • Zero

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

  • 1.02

  • 0.98

  • 0.90

  • -$108,120

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

  • It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

  • It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

  • It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

  • It is a term used to describe activities that are core project management processes, but not core project activities.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?