Construction 2 - 1 semester exam

Construction 2 - 1 semester exam

12th Grade

30 Qs

quiz-placeholder

Similar activities

Mechanical Drawing - 1.1.2.

Mechanical Drawing - 1.1.2.

8th - 12th Grade

25 Qs

Rules for Base Cabinets

Rules for Base Cabinets

12th Grade

28 Qs

Intro to STS-Construction Review

Intro to STS-Construction Review

9th - 12th Grade

30 Qs

Construction Documents Quix

Construction Documents Quix

9th - 12th Grade

28 Qs

Mechanical, Electrical and Plumbing Construction Drawings Quiz

Mechanical, Electrical and Plumbing Construction Drawings Quiz

12th Grade

25 Qs

Intro to Construction POST-test Review

Intro to Construction POST-test Review

9th - 12th Grade

28 Qs

Construction Test views/scale/lines

Construction Test views/scale/lines

6th - 12th Grade

25 Qs

Floor and Wall Framing

Floor and Wall Framing

9th - 12th Grade

31 Qs

Construction 2 - 1 semester exam

Construction 2 - 1 semester exam

Assessment

Quiz

Architecture

12th Grade

Hard

Created by

Ashton Mckelley

Used 1+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

A 2 ̋ x 4 ̋ measuring 8 ́-0 ̋ or 96 ̋ is to be cut into 22 ̋ pieces for blocking. If 200 pieces of blocking are needed, how many 2 ̋ x 4 ̋ x 8 ́-0 ̋ lengths are needed?

47A

46B

45C

44D

2.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

Siding can be installed at a rate of 175 square feet per carpenter per day. A crew of 4 carpenters is working on a house containing 5600 square feet of siding. The carpenters work 8 hour days. How many man-days will it take?

10A

9B

8C

7D

3.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

Siding can be installed at a rate of 175 square feet per carpenter per day. A crew of 4 carpenters is working on a house containing 5600 square feet of siding. The carpenters work 8 hour days. How many man hours will it take the carpenters to finish siding the house?

312A

413B

250C

256D

4.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

Rafters are to be installed on a structure that measures 128 ́-0 ̋ long. Required spacing is 16 ̋ on center. How many sets of rafters are required? Note: Add 1 rafter for a starter.

97A

96B

100C

101D

5.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

The following material list was compiled for a framing project. Out of all of the pieces needed for the project, how many total 2x4 are needed?

65A

431B

108C

352D

6.

MULTIPLE SELECT QUESTION

30 sec • 20 pts

An apprentice program has the following number of apprentices enrolled in each section. What is the total number of Carpenters, Millwright and Pre-Apprentice apprentices enrolled in the program?

1743A

1024B

1226C

1300D

7.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

A crew of carpenters frames a roof using various trusses and braces. The package includes 96 king post trusses, 75 scissor trusses, 31 2 x 4 x 16 ́ -0 ̋ braces, and 2 gable end trusses. Each truss requires 8 2 x 4 x 16'-0" to build. How many total 2 x 4's are needed, including bracing, are required for completion?

1405A

1632B

1234C

1350D

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?