Quiz 5 - Project Management

Quiz 5 - Project Management

University

18 Qs

quiz-placeholder

Similar activities

KIBANGENGE COMPREHENSIVE SCHOOL GRADE 5 AGRICULTURE AND NUTRITIO

KIBANGENGE COMPREHENSIVE SCHOOL GRADE 5 AGRICULTURE AND NUTRITIO

5th Grade - University

21 Qs

Personal Finance Vocabulary

Personal Finance Vocabulary

8th Grade - University

16 Qs

Manajemen Proyek Quiz

Manajemen Proyek Quiz

University

20 Qs

Home Maintenance

Home Maintenance

10th Grade - University

15 Qs

Interpersonal Relationships Introduction

Interpersonal Relationships Introduction

University

16 Qs

Mass Flowers

Mass Flowers

University

17 Qs

States of Matter Quiz

States of Matter Quiz

12th Grade - University

15 Qs

Phi Meeting

Phi Meeting

University

13 Qs

Quiz 5 - Project Management

Quiz 5 - Project Management

Assessment

Quiz

Life Project

University

Medium

Created by

Sergio Monteiro

Used 1+ times

FREE Resource

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
Cost Variance
Management Overhead
Management Contingency Reserve
Schedule Variance

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If the Earned Value is equal to Actual Cost, it means:
Project is on budget and on schedule
Schedule Variance Index is 1
There is no schedule variance
There is no cost variance

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If earned value EV = 350, actual cost AC = 400, planned value PV = 325, what is cost variance CV ?
350
-75
400
-50

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the best way to maintain control of costs?
Evaluate monthly expenditures based on a carefully formulated program
Personally review all expenditures before any disbursements are made
Assign all authority to one staff memeber
Submit weekly expenditures to superior for review

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You found out that your project is one week late, as an effective project manger, what would you do?
Evaluate resources and options
Analyze why the deadline was not met
Inform the client that the project will be one week late
Ask to work overtime

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As a project manager you are estimating the cost of your project activities using BETA distribution. For a particular project activity, your optimistic estimate is 41, pessimistic estimate is 77 and most Likely estimate is 53. What would be the expected cost for this activity?
171
55
59
57

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are the MOST important to deriving the total funding requirements and periodic funding requirements of the project?
Management Reserve and Contingency Reserve
Cost Baseline and Management Reserve
Funding Limit Reconciliation
Project Budget and Contingency Reserve

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?