Lesson 4 - Project Staffing and Management
Authored by Yến Điền
Professional Development
12th Grade
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
9 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project staffing, the primary role of senior management is in the selection of the:
Project manager
Assistant project managers
Functional team
Executives do not get involved in staffing.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project staffing, the primary role of line management is:
Approving the selection of the project manager
Approving the selection of assistant project managers
Assigning functional resources based upon who is available
Assigning functional resources based upon availability and the skill set needed
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is far more likely to succeed if it is obvious to everyone that:
The project manager has a command of technology.
The project manager is a higher pay grade than everyone else on the team.
The project manager is over 45 years of age.
Executive management has officially appointed the project manager.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Most people believe that the best way to train someone in project management is through:
On-the-job training
University seminars
Graduate degrees in project management
Professional seminars and meeting
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
In staffing negotiations with the line manager, you identify a work package that requires a skill set of a grade 7 worker. The line manager informs you that he will assign a grade 6 and a grade 8 worker. You should:
A. Refuse to accept the grade 6 because you are not responsible for training
B. Ask for two different people
C. Ask the sponsor to interfere
D. Be happy! You have two workers
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
You priced out a project at 1,000 hours assuming a grade 7 employee would be assigned. The line manager assigns a grade 9 employee. This will result in a significant cost overrun. The project manager should:
A. Reschedule the start date of the project based upon the availability of a grade 7
B. Ask the sponsor for a higher priority for your project
C. Reduce the scope of the project
D. See if the grade 9 can do the job in less time
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
As a project begins to wind down, the project manager should:
A. Release all nonessential personnel so that they can be assigned to other projects
B. Wait until the project is officially completed before releasing anyone
C. Wait until the line manager officially requests that the people be released
D. Talk to other project managers to see who wants your people
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?