Week 5 (PM 5.00) Practice Test (EVM)

Week 5 (PM 5.00) Practice Test (EVM)

11th Grade

25 Qs

quiz-placeholder

Similar activities

Client Requirements

Client Requirements

9th - 12th Grade

21 Qs

Photoshop Units 1 - 6 Vocabulary  Review

Photoshop Units 1 - 6 Vocabulary Review

9th - 12th Grade

20 Qs

Understanding Relational Data Models: SQL

Understanding Relational Data Models: SQL

11th Grade

20 Qs

InDesign q1

InDesign q1

9th - 12th Grade

25 Qs

ALAM NG ICT 2 YAN!

ALAM NG ICT 2 YAN!

11th Grade

20 Qs

iMovie App Quiz

iMovie App Quiz

6th - 12th Grade

20 Qs

UH_TIK_XI

UH_TIK_XI

11th Grade

20 Qs

iMedia Part 2

iMedia Part 2

9th - 11th Grade

20 Qs

Week 5 (PM 5.00) Practice Test (EVM)

Week 5 (PM 5.00) Practice Test (EVM)

Assessment

Quiz

Computers

11th Grade

Easy

Created by

Bobbie Jones

Used 2+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team has a renovation project that has a budget of $1,500 and is 40% complete. The team planned to spend $500 each month during the 3-month project timeline. At the end of the first month, the team evaluates their progress. At this point, what is the project's planned value?

$500

$600

$1,000

$500

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project with a budget of $2,000 and a timeline of 5 months, if the team planned to spend $300 each month, what is the Planned Value at the end of the second month?

$600

$900

$1,200

$1,500

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has a Budget at Completion (AC) of $10,000 and a cumulative earned value of $8,000. What is the Cost Variance (CV)?

$2,000

$10,000

-$8,000

-$2,000

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Planned Value (PV) for a project is $5,000, the Earned Value (EV) is $4,000, and the Actual Cost (AC) is $6,000. What is the Schedule Variance (SV)?

$2,000

-$2,000

$1,000

-$1,000

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has a Schedule Performance Index (SPI) of 1.2. What does this indicate about the project's schedule performance?

Behind schedule

On schedule

Ahead of schedule

Cannot be determined

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Cost Performance Index (CPI) for a project is 0.9. What does this indicate about the project's cost performance?

Over budget

On budget

Under budget

Cannot be determined

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a project has a Budget at Completion (BAC) of $20,000, Earned Value (EV) of $15,000, and Actual Cost (AC) of $18,000, what is the Cost Performance Index (CPI)?

0.75

0.83

0.90

1.25

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?