Module 4 (PART 2) Energy Isolation Certificate Quiz

Module 4 (PART 2) Energy Isolation Certificate Quiz

12th Grade

9 Qs

quiz-placeholder

Similar activities

AP Biology Evolution CH 21-25

AP Biology Evolution CH 21-25

11th - 12th Grade

12 Qs

TLA 3.3 BJT Familiarization

TLA 3.3 BJT Familiarization

11th Grade - University

10 Qs

Med Term Suffixes

Med Term Suffixes

9th - 12th Grade

10 Qs

our galaxy planet

our galaxy planet

4th Grade - Professional Development

10 Qs

Evolution (Zoo)

Evolution (Zoo)

10th - 12th Grade

11 Qs

Natural Selection, Darwin, and Evolution

Natural Selection, Darwin, and Evolution

9th - 12th Grade

13 Qs

The Universe

The Universe

5th - 12th Grade

5 Qs

Quiz: Species, Extinction, and Speciation

Quiz: Species, Extinction, and Speciation

12th Grade

10 Qs

Module 4 (PART 2) Energy Isolation Certificate Quiz

Module 4 (PART 2) Energy Isolation Certificate Quiz

Assessment

Quiz

Science

12th Grade

Hard

Created by

Christopher Blake

Used 27+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

9 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the Energy Isolation Certificate (IC)?

Record work completion

Ensure safe work practices and communication

Update plant integrity

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for completing the Application Section of the Energy Isolation Certificate (IC)?

Area Authority (AA)

Isolating Operator (ISO)

Asset Owner

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When is a Sanction To Test (STT) required?

At the end of the work shift

During pre-start ups

After permit expiration

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Isolation Authority (ISA) confirm in the Mechanical Isolation Details?

Work scope details

De-isolation sequence

Integrity of isolations

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who approves the de-isolation of equipment in the Electrical Energy Isolation Certificate?

Isolating Operator (ISO)

Area Authority (AA)

Permit Issuer (PI)

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When should the Isolating Operator (ISO) sign off on the Isolation Certificate (IC) during the de-isolation process?

Before the independent verification

After the closure by Area Authority (AA)

Before the approval by AA

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who determines whether an independent verification is required for isolation points?

Isolating Operator (ISO)

Area Authority (AA)

Permit Issuer (PI)

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the Dynamic Risk Assessment process?

Confirm isolations

Monitor hazards and assess risks

Update the Isolation Certificate

9.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the minimum acceptable standard of final isolation for intrusive and non-intrusive maintenance?

Maximum Isolation Standard

Baseline Isolation Standard

Advanced Isolation Standard