ACS CCN1 Quiz 1

ACS CCN1 Quiz 1

Professional Development

11 Qs

quiz-placeholder

Similar activities

course 5001

course 5001

Professional Development

14 Qs

Gas Installation and Tightness Test Quiz

Gas Installation and Tightness Test Quiz

Professional Development

15 Qs

PP9 Sanitation

PP9 Sanitation

Professional Development

14 Qs

Phase4.mod9ECV

Phase4.mod9ECV

Professional Development

6 Qs

QUIZ MODULE 3 CEPBFO

QUIZ MODULE 3 CEPBFO

Professional Development

10 Qs

Cuestionario sin título

Cuestionario sin título

Professional Development

10 Qs

electrical science 202

electrical science 202

Professional Development

14 Qs

Tightness Testing and IGEM/UP/1B

Tightness Testing and IGEM/UP/1B

Professional Development

10 Qs

ACS CCN1 Quiz 1

ACS CCN1 Quiz 1

Assessment

Quiz

Science

Professional Development

Hard

Created by

Rob Anderson

Used 35+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the maximum installation volume (IV) that can be worked on as per IGEM/UP/1B?

0.025m3

0.035m3

0.02m3

0.2m3

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the maximum operating pressure (MOP) at the outlet of the emergency control valves (ECV) as per IGEM/UP/1B?

75mb

1bar

2bar

3bar

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the maximum nominal bore for copper pipework as per IGEM/UP/1B?

22mm

28mm

35mm

45mm

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the IV & PV of the installation specified below?

G4 meter (0.008)

22mm copper pipe (0.00032)

There is 6m of 22mm copper pipe

0.002 & 0.003

0.008 & 0.0012

0.009 & 0.0013

0.010 & 0.015

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When conducting a let-by test the water within the U gauge raises by more than 0.25mb, what procedure would you follow?

The test would be stopped and ESP called to repair

Move straight onto the tightness test suspected let-by would have no detrimental affect on the test.

Connect temporary bonding across the meter than disconnect the ECV and spray LDF into the barrel to prove let-by before contacting ESP.

Disconnect the ECV and spray LDF into the barrel to prove you have let-by.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

      What is the maximum pressure drop allowed for an existing system with appliances fitted, a G4 meter and 35mm pipework, appliance connected and no smell of gas reported?

4mb

0mb

8mb

2.5mb

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The normal working pressure of a low pressure installation is?

19mb

20mb ± 1mb

21mb ± 2mb

23mb

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?