Quiz PMI-PBA (day-1)
Authored by Training eNetwoQ ServIT Indonesia
Professional Development
Professional Development
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What is the output of product scope decomposition?
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which one of the following is TRUE for the Use Case Model :
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are a Business Analyst for manufacturing hybrid, high speed motorbike project. During requirement gathering workshop team encounters requirements like; Bike should be able be reliable to drive in all-weather condition, it should meet safety standards of driving at 150km/hour in wintery conditions and should have good supportability. As a project manager how BEST would you categorize such requirements?
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are the business analyst for a large one year telecommunication project. The project involves 3 different sellers, and a project team of 30 people. You are defining communication approach about what information will be communicated, about how stakeholders wish to receive information on requirements and how often they wish to receive information. Where are you documenting this information?
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following statement is NOT true with respect to requirement management plan?
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are the business analyst for a smaller project where there are few requirements. Management would still like you to create a method to trace the few requirements for this project. What type of matrix would be best in this instance?
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Sally as a business analyst, has done with business analysis planning, and elicitation of requirements. Now she needs to analyse, validate, verify and approve the requirements. Senior business analyst, David asked Sally to refer grouping of stakeholders in business analysis planning based on their business, technical and industry experience. Sally is confused as to why it is needed to refer stakeholders experience for validating and approving requirements. What could be the reason?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?