PM - Lesson 5

PM - Lesson 5

University

18 Qs

quiz-placeholder

Similar activities

Phrases in Business English

Phrases in Business English

University

13 Qs

The best company related stuff test. idk...

The best company related stuff test. idk...

University

13 Qs

Pathways 3 Unit 3 - Reading 2 comprehension

Pathways 3 Unit 3 - Reading 2 comprehension

University

16 Qs

Elementary English Teaching Methods (Methods)

Elementary English Teaching Methods (Methods)

University

20 Qs

Unit 3 Review Bussiness Partner

Unit 3 Review Bussiness Partner

University

15 Qs

DAY 11 (26-50)

DAY 11 (26-50)

University

22 Qs

PM - Lesson 5

PM - Lesson 5

Assessment

Quiz

English

University

Hard

Created by

Phan Trinh

FREE Resource

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The document that officially sanctions the project is the:

A. Project charter

B. Project plan

C. Feasibility study

D. Cost-benefit analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work breakdown structure “control points” for the management of a project are the:

A. Milestones

B. Work packages

C. Activities

D. Constraints

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One of the most common reasons why projects undergo scope changes is:

A. Poor work breakdown structure

B. Poorly defined statement of work

C. Lack of resources

D. Lack of funding

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following generally cannot be validated using a work breakdown structure?

A. Schedule control

B. Cost control

C. Quality control

D. Risk management

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of WBS element 1.2.2.0 is:

A. $20K

B. $30K

C. $50K

D. Cannot be determined

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of WBS element 1.1.1 is:

A. $12K

B. $13K

C. $25K

D. Cannot be determined

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of the entire program (1.00.00) is:

A. $25K

B. $66K

C. $91K

D. Cannot be determined

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?