Hot Water Systems Quiz L3P2U6,1.8;3

Hot Water Systems Quiz L3P2U6,1.8;3

Professional Development

7 Qs

quiz-placeholder

Similar activities

Site Procedures and Planning PT9

Site Procedures and Planning PT9

Professional Development

10 Qs

Traditional Foods

Traditional Foods

KG - Professional Development

10 Qs

The Star Wars Quiz

The Star Wars Quiz

5th Grade - Professional Development

11 Qs

Pendawaian Pembuluh Logam

Pendawaian Pembuluh Logam

Professional Development

11 Qs

Peach Vs. Mario Team Rally Tour Quiz

Peach Vs. Mario Team Rally Tour Quiz

KG - Professional Development

10 Qs

Thermal Insulation

Thermal Insulation

Professional Development

10 Qs

Paket 4 Master GLD

Paket 4 Master GLD

Professional Development

10 Qs

Definir la estrategia de Expansión

Definir la estrategia de Expansión

Professional Development

11 Qs

Hot Water Systems Quiz L3P2U6,1.8;3

Hot Water Systems Quiz L3P2U6,1.8;3

Assessment

Quiz

Other

Professional Development

Hard

Created by

Craig Boothright

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the three sections of the discharge pipework?

Tundish, D2, D1

Tundish, D1, D2

D1, D2, Tundish

D1, Tundish, D2

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to the regulations, what should be the minimum diameter of the D1 pipework?

28mm

22mm

One size larger than the outlet of the safety device

Same as the outlet of the safety device

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the basic formula for determining the size of the D2 pipework?

Same size as the D1 pipework

Depends on the length of the pipe run

Two sizes larger than the D1 pipework

One size larger than the D1 pipework

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the maximum resistance allowed for a straight length of 35mm copper discharge pipe from a G¾ temperature relief valve?

1.0m

1.4m

1.7m

2.3m

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If the D2 discharge pipe is to be run in 22mm pipe and has 2 elbows or bends fitted, what is the maximum pipe run?

9.6m

8.0m

10.2m

7.4m

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

From a G1/2 TPRV With a proposed length for a D2 pipework of 6m and requiring 6 bends what would the equivalent length, and pipe D2 diameter be?

12.0m @28mm

9.0m @22mm

6.0m @28mm

4.2m @ 35mm

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the minimum pipe size that could be used for a D2 pipework run that is 8m in length and requires 5 bends?

22mm

42mm

28mm

35mm