15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
___project management approach is most appropriate when business needs change frequently.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A sprint in agile project management is:
a short, time-boxed period during which a specific amount of work is completed.
a meeting to discuss project progress.
a document outlining project goals.
a period of time with no work being done.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the goal/objective of a sprint/iteration in agile?
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
___is a small function or deliverable that addresses a business need.
feature
sprint
iteration
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which is NOT an advantage of agile project management?
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main difference between waterfall approach and agile approach?
the sequential vs. iterative nature of the approaches.
the level of collaboration and communication in waterfall approach compared to agile approach.
the level of flexibility in waterfall approach compared to agile approach.
the documentation required in waterfall approach but not in agile approach.
7.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Which is NOT a stage in the agile methodology?
Explore
Speculate
Close
Execute
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?