CAPM |Day 4

CAPM |Day 4

Professional Development

5 Qs

quiz-placeholder

Similar activities

Importing and Exporting - Module 4:  Plan and Prepar for Export

Importing and Exporting - Module 4: Plan and Prepar for Export

Professional Development

10 Qs

Business Communication Review

Business Communication Review

Professional Development

10 Qs

ISO 9001:2015 Quality Management System Awareness - AM

ISO 9001:2015 Quality Management System Awareness - AM

Professional Development

10 Qs

SALES PLANNING CHAPTER 5

SALES PLANNING CHAPTER 5

Professional Development

10 Qs

BA Revision Session 4 - Business Fundamentals

BA Revision Session 4 - Business Fundamentals

Professional Development

10 Qs

Pop Quizz #2

Pop Quizz #2

Professional Development

5 Qs

AgilePM (LC, Roles, Products, TB)

AgilePM (LC, Roles, Products, TB)

Professional Development

7 Qs

Marketing Objectives For IB Diploma

Marketing Objectives For IB Diploma

11th Grade - Professional Development

10 Qs

CAPM |Day 4

CAPM |Day 4

Assessment

Quiz

Business

Professional Development

Medium

Created by

Ahmed Abdessalem

Used 1+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Agile Manifesto states, “We value individuals and interaction over comprehensive documentation?” True False

True

False

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Often before a project starts, business analysts or engineers conduct a needs assessment for project approval and funding. Which two of the following are items identified or specified in a needs assessment for a new project? (Choose two)

The project manager

Business goals and objectives

Potential constraints, assumptions, risks and dependencies

Individual or department who will handle procurement invoices

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which three of the following are a financial-based benefit measure method? (Choose three)

Net present value

Internal rate of return

Return of investment

Net Promoter Score

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The business determines that the project you are managing must be based on a plan-driven project management approach. This is partially due to the SMART objectives the steering committee has set for the project. In the acronym SMART, what does the T stand for?

Technical

Tentative

Timely

Testable

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is the best elicitation technique to use when your project team wants to facilitate a discussion with a certain set of users to get a better understanding on how they might use your project’s product?

Document analysis

Focus group

Benchmarking

Plurality