
RISK-BASED INSPECTION (RBI)
Authored by Nurul Izni Md Amin
Professional Development
Professional Development
Used 6+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
What is Risk Based Inspection?
The Risk-Based Inspection (RBI) methodology is used to manage the overall risk of a plant by focusing inspection efforts on the equipment with the highest risk
The Risk-Based Inspection (RBI) is software used for calculation of consequences of failure
The Risk-Based Inspection (RBI) methodology is used to manage the overall probabilities of failures of a plant by focusing mitigation efforts on the equipment with the highest risk
The Risk-Based Inspection (RBI) is a standard used to manage the overall risks of failures in a plant by focusing on the equipment in ALARP region
2.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
Act vs Code/Standard? Which one should to comply?
Act is the highest authority to be complied, if the Act more stringent than standard, then should follow the Act/Regulation
Code/Standard is the highest authority to be complied, if the standard more stringent than act, then should follow the Code/Standard
3.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
Which code / standard should be use during pre-construction & in service?
Pre-cons: API,
In service: ASME Sec I
Pre-cons: ASME Sec I, In service: API
Pre-cons: ASME PCC 2,
In service: API
4.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
How many types of RBI analysis/assessment?
2-Qualitative, Quantitative
2-Semi, Quantitative
3-Qualitative, Semi, Quantitative
5.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
What is factors to be considered in LOF/POF evaluation?
Health and Safety Impact
Human and operator errors
External condition
Earthquakes
6.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
What is factors to be considered in COF evaluation?
Human error
Natural disasters
External events
Environment, Business impact
7.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
How the process to implement RBI?
Data collection -> Damage mechanism identification -> Risk assessment -> Risk Ranking -> Mitigation -> Insp. Plan -> Reassessment
Data collection -> Damage mechanism identification -> Risk assessment -> Risk Ranking -> Insp. Plan -> Mitigation -> Reassessment
Data collection -> Risk assessment -> Risk Ranking -> Insp. Plan -> Damage mechanism identification-> Mitigation -> Reassessment
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
DAY 3 ASSESSMENT - TOT ON POSTHARVEST HANDLING
Quiz
•
1st Grade - Professio...
10 questions
Sepsis Materna
Quiz
•
Professional Development
10 questions
Pretest WMS
Quiz
•
Professional Development
15 questions
Termos em inglês em Agile SCRUM
Quiz
•
Professional Development
15 questions
Google Ads Fundamentals
Quiz
•
Professional Development
10 questions
Training Recap
Quiz
•
Professional Development
10 questions
Einteilung der Werkstoffe
Quiz
•
Professional Development
10 questions
EP Spirit to Support 800 by achieving Target Zero
Quiz
•
Professional Development
Popular Resources on Wayground
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
15 questions
Valentine's Day Trivia
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade