Project Management Processes

Project Management Processes

Professional Development

26 Qs

quiz-placeholder

Similar activities

Grant Writing

Grant Writing

Professional Development

21 Qs

Project vs. PBL

Project vs. PBL

Professional Development

23 Qs

Lesson-4 Lead The Project Team

Lesson-4 Lead The Project Team

Professional Development

22 Qs

Chapter 5: Digital and Social Media Marketing

Chapter 5: Digital and Social Media Marketing

University - Professional Development

23 Qs

Chap2. Establishing a PPP Framework

Chap2. Establishing a PPP Framework

Professional Development

25 Qs

Aptitude Test for CA

Aptitude Test for CA

Professional Development

25 Qs

Jira Quiz-2

Jira Quiz-2

Professional Development

25 Qs

SBILD Kochi-T20 Day 4

SBILD Kochi-T20 Day 4

Professional Development

21 Qs

Project Management Processes

Project Management Processes

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Eboni Morris

Used 2+ times

FREE Resource

26 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which project management process group is the details project budget created?

Initiating

Before the project management process

Planning

Executing

Answer explanation

Notice the use of the word "detailed". Such a budget is created during the project planning phase.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project charted is created in which project management group?

Executing

Planning

Closing

Initiating

Answer explanation

The project charter is needed before the planning and execution of the work can begin. Therefore it is created and approved in project initiating.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project team has just competed the initial project schedule and budget. The NEXT thing to do is to:

Identify risks

Begin iterations

Determine communication requirements

Create a bar (Gantt) chart

Answer explanation

Communications requirements and quality standards are needed before risks can be determined. Iterations cannot begin until risks are identified, qualified, and quantified, and responses are developed. Through iterations, the WBS and other parts of the project management plan are revised. A bar chart would have been done during the creation of the schedule, so it cannot be the NEXT thing.

Of the choices listed, determine communications requirements is the best option.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A detailed project schedule can be created only after creating the:

Project budget

Work Breakdown Structure

Project management plan

Detailed risk assessment

Answer explanation

In the project management process, the project budget, detailed risk assessment, and project management plan come after the schedule is created. The only answer that could be as input is the WBS.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The person who should be in control of the project during Project Planning is the:

Project manager

Team member

Functional Manager

Sponsor

Answer explanation

A project manager should be named early in the project, during project initiating, if possible. It is then their responsibility to control the project throughout its life.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT an input to the initiating Process group?

Company Processes

Company Culture

Historical WBS

Project Scope Management

Answer explanation

The project scope statement is an output of project planning.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project sponsor has just signed the project charter. What is the NEXT thing to do?

Being to complete the work packages.

Validate Scope

Start integrated change control.

Start to create management plans.

Answer explanation

The project charter is created during project initiating. Completing work packages is done during project executing. Validating scope and performing integrated changes control are done during project monitoring and controlling. Started to create management plans is the best choice, as it is part of project planning, which takes place after Initiating has been completed.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development