Quiz Mini SG PMP - PMP Domain 1 People

Quiz Mini SG PMP - PMP Domain 1 People

Professional Development

25 Qs

quiz-placeholder

Similar activities

PMP Questions 6th Edition Quiz 1

PMP Questions 6th Edition Quiz 1

Professional Development

20 Qs

PMP Integration Management-AC 2019

PMP Integration Management-AC 2019

Professional Development

25 Qs

Project Management 101

Project Management 101

Professional Development

20 Qs

PMP Questions Agile Management 5

PMP Questions Agile Management 5

Professional Development

20 Qs

Project Management - SEA-TVET

Project Management - SEA-TVET

Professional Development

20 Qs

Pmp Lesson 9

Pmp Lesson 9

Professional Development

30 Qs

PMP Lesson 8.1

PMP Lesson 8.1

Professional Development

30 Qs

ROAD PMP

ROAD PMP

Professional Development

25 Qs

Quiz Mini SG PMP - PMP Domain 1 People

Quiz Mini SG PMP - PMP Domain 1 People

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Training eNetwoQ ServIT Indonesia

Used 1+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You have just completed the project, at the end of the project. You want to check whether is successful for benefit which it was started, which document you will check for this?
A. Benefit management plan
B. Business case
C. Project chanter
D. Project management plan

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You have been just hired as the project manager, project charter has been approved. What will your first step as project manager?
A. Review business case and make it is aligned with organization strategy
B. Review project charter to understand requirements
C. Identify stakeholder
D. Make assumption log

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You are the project manager in large Construction project, You have review project charter. You are in initiation process. There is a chance that some resources will leave the project. At this stage which document you will update to document this?
A. Project charter
B. Stakeholder register
C. Assumption log
D. Risk register

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You are the project manager working in large petroleum company. You are in the process of identifying stakeholder. You have one stakeholder, he is very important for the project. Not managing him can make or break your project. You have find out he is resistant to the project. As this may cause removal of his team members. What will be strategy to engaged that stakeholder?
A. Send him daily report
B. Call him to see how you can make him neutral
C. Meet him personally to find out the reason
D. Send your team members to talk to him

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

During execution phase a new stakeholder has been identified. You have analyzed him. He is very important for the project. You have added him stakeholder register what will you do next?
A. Update stakeholder register
B. Update stakeholder plan
C. Update communication plan
D. Raise a change request

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

As a project manager, you are leading a project, where you have twelve programmers. Two of them have just handed in their letters of resignation. This realized risk had been identified and accounted for during the planning stage of the project. If no action is taken, you will not meet your deadlines. What should you do next?
A. Crash the schedule
B. Submit a change request to update the schedule baseline
C. Review the risk register
D. Perform the Plan Risk Responses process

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Once a month, you attend a steering committee meeting to report on project status as specified in the communications management plan. During the meeting, the committee members challenge you on the productivity of your project team, pointing out that your team has a velocity of 40 story points per sprint, while another project team is averaging 80 points per sprint. What is your best course of action?
A. During the next sprint planning meeting, direct your team to complete 80 story points for the sprint
B. Repeat the Acquire Resources process to double the size of the team to achieve 80 story points per sprint
C. Submit a change request to update the project schedule with the actual velocity of the team
D. Take the opportunity to coach the steering committee members on the proper use of the velocity metric

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?