Prestressed Concrete HW 1b

Prestressed Concrete HW 1b

Professional Development

10 Qs

quiz-placeholder

Similar activities

GSC Olympics: Difficult Round

GSC Olympics: Difficult Round

Professional Development

15 Qs

SAK MIDTERM QUIZ-CMT 102

SAK MIDTERM QUIZ-CMT 102

Professional Development

15 Qs

Connaissances de la mécanique humaine

Connaissances de la mécanique humaine

Professional Development

15 Qs

DPM Yeg - the innovation edition

DPM Yeg - the innovation edition

Professional Development

9 Qs

Josh DWI Quizz

Josh DWI Quizz

Professional Development

15 Qs

Skeletal and Muscular Systems

Skeletal and Muscular Systems

Professional Development

14 Qs

Dr Pepper

Dr Pepper

Professional Development

10 Qs

Aircraft Mass and Balance - SEP 1

Aircraft Mass and Balance - SEP 1

Professional Development

15 Qs

Prestressed Concrete HW 1b

Prestressed Concrete HW 1b

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Piledriverob Piledriverob2375

Used 14+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Do not start any transition curvature in a Tendon closer than_____ from the stressing Anchorage.

12 INCHES

6 inches

12 inches plus 1

Answer explanation

FIELD MANAUL fig. 4-4

SPECIFICATIONS 3.7.5.3

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Beam Tendons should be supported at a maximum spacing of ?

48 INCHES

24"

13"

Answer explanation

FIELD MANUAL 4.5.2

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Couplers should only be used at locations approved by the _________.

LDP

License

Design

Professional

supervisor

foreman

Answer explanation

FIELD MANUAL 9.10.3

SPECIFICATIONS 2.4.3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Extension cords for stressing equipment at a minimum should be three-wire, 12 gauge & less than ______ in length

100 FEET

50'

1000'

Answer explanation

FIELD MANULA 6.3.(g)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Proper concrete consolidation is most critical at the ___________.

ANCHORAGE ZONE

midspan

entire pour

Answer explanation

FIELD MANUAL 5.1.3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A minimum clear distance of ______ should be maintained between PT Tendons & blocked out openings.

3 INCHES

6 inches plus 1

12 inches

Answer explanation

FIELD MANUAL 4.4.19

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Tape used as a component for sheathing repairs shall have a minimum width of _____.

2 INCHES

1-1/2 inches

6 inches

Answer explanation

SPECIFICATIONS 2.4.3.2

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development