What is the primary goal of the Develop Schedule process in the Schedule Management knowledge area?

Project Schedule Management Knowledge area

Quiz
•
Professional Development
•
Professional Development
•
Hard
Mariam Nazaryan
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To create a detailed task list.
To determine project resource requirements.
To estimate project costs.
To establish the project schedule baseline.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During which process is the critical path determined?
Plan Schedule Management.
Estimate Activity Durations
Develop Schedule.
Control Schedule.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of the Control Schedule process?
To adjust project scope.
To monitor project risks.
To track project performance against the schedule baseline.
To create a detailed task list.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the Control Schedule process, what does "rebaseline" refer to?
Changing the project scope
Updating the project's risk register.
Creating a new project schedule baseline.
Adding new tasks to the project.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which process involves decomposing project work into smaller, manageable activities to facilitate schedule development?
Plan Schedule Management.
Define Activities.
Estimate Activity Resources.
Develop Schedule.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager is working on a construction project with a fixed completion date. Due to unexpected delays, the project is at risk of not meeting the deadline. What should the project manager do first?
Adjust the project scope to align with the new schedule.
Communicate the issue to stakeholders and assess the impact.
Delegate the issue to the team to find a solution.
Implement additional resources to accelerate tasks.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the Control Schedule process, the project manager identifies that the project is falling behind the schedule baseline. What corrective action should the project manager take?
Adjust the project scope to accommodate the delays.
Rebaseline the schedule to reflect the delays.
Implement corrective measures to get the project back on track.
Continue as planned, as minor schedule deviations are acceptable.
Create a free account and access millions of resources
Similar Resources on Wayground
11 questions
Basics of Project management

Quiz
•
Professional Development
10 questions
Project Management Fundamentals - Module 5

Quiz
•
Professional Development
6 questions
Schedule Management Processes - Assignment

Quiz
•
Professional Development
15 questions
Scope Management Plan

Quiz
•
Professional Development
7 questions
Project Scope

Quiz
•
Professional Development
9 questions
Planning and Scheduling Professional Practice Questions

Quiz
•
Professional Development
10 questions
Introduction to Project Management

Quiz
•
Professional Development
10 questions
Project Integration Revision

Quiz
•
Professional Development
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade