
PMI BC Quiz 1
Authored by PMI Trainer
Professional Development
Professional Development
Used 6+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
45 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A customer is considering appending new features to the project deliverable. Before a project team member begins working on these new features, which is a mandatory step?
Gain approval from the Project Manager
Gain approval from the Project Sponsor
Ensure the change control board (CCB) approves
Ensure key subject matter experts (SMEs) approve
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project is at the planning stage of the project. The Project Manager realizes that producing a complicated multi-functional application is not feasible with the current resources and decides to hire more resources to produce the application. The Project Manager identifies and contracts short-term resources. Which of the following risk response strategy represent this scenario?
Mitigate
Transfer
Accept
Avoid
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A Project Manager has performed the following steps:
I. Finished a major IT deployment project.
II. Confirmed with the release manager that all systems are working.
III. Confirmed that functionality has been verified by the quality assurance team.
IV. Informed the customer.
Which of the following is the next step the Project Manager should take?
Update the risk register, stakeholders, and team members
Add the lessons learned to the organization knowledge base
Ensure that the procurement plan is closed out
Review, verify, and complete the release documentation
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
After realizing that a lack of resources on a project with an increasingly high workload, management outsources some significant tasks to keep the project on schedule. What should the Project Manager do in this situation?
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project has the following need: I. Nine hundred resource hours must be outsourced. II. Because of internal policies, all providers must be provided with the same information about the requirements. Which of the following action should the Project Manager take to ensure this?
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A company has a goal of increasing customer satisfaction within four months. A project is initiated to meet this goal. The Project Manager needs to identify best practices. Which of the following, the Project Manager should utilize to achieve this?
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When a customer identifies performance issues with this product, a new product is released. The Project Manager realizes that cost of quality (COQ) should have been used to estimate this cost. Which of the following category of COQ should the Project Manager have used?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?