Earned Value
Quiz
•
Education
•
1st - 5th Grade
•
Practice Problem
•
Hard
khemaies bahri
Used 9+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Si EV = 1200, PV = 1000 et AC = 1500, Calculer CV
-300
300
-200
200
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Si EV = 1200, PV = 1000 et AC = 1500, Calculer SV
-300
300
-200
200
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Si EV = 1200, PV = 1000 et AC = 1500, Calculer SPI
125%
83%
120%
80%
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
CV > 0
Dépassement du budget
Dépassement du délai
Gain sur le budget
Gain sur le délai
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
SV > 0
Dépassement du budget
Dépassement du délai
Gain sur le budget
Gain sur le délai
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
SPI = 120%
Perte de 20% sur le budget
Pour chaque dinar dépensé on gagne 1,200 dinar
l’avancement est de 120 % celui planifié
Retard de 20% sur le délai
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
CPI = 80%
Gain de 20% sur le budget
Pour chaque dinar dépensé on récupère 0,8 dinar
l’avancement est de 80 % celui planifié
Gain de 20% sur le délai
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
12 questions
Bilan radiatif
Quiz
•
KG - 5th Grade
15 questions
Thème 4 grammaire
Quiz
•
2nd Grade
10 questions
การบวก การลบ เศษส่วน
Quiz
•
5th Grade
15 questions
Tes Sumatif IPAS Kelas 4 BAB 5
Quiz
•
4th Grade
14 questions
Électricité/électronique
Quiz
•
1st Grade
15 questions
Ulangkaji prinsip akaun *kuiz2 @4ak2
Quiz
•
1st - 3rd Grade
15 questions
Kuis Fungsi Manajemen
Quiz
•
2nd Grade
11 questions
Símbolos Patrios 2
Quiz
•
2nd - 3rd Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Education
18 questions
CA # 4 2025
Quiz
•
2nd Grade
12 questions
3rd Grade Editing and Revising Practice Quiz
Quiz
•
3rd Grade
15 questions
Long E (e, ee, ea)
Quiz
•
1st Grade
16 questions
Equivalent Fractions
Quiz
•
5th Grade
10 questions
Ivan Vocab #5
Quiz
•
3rd Grade
20 questions
IREAD: Homonyms
Quiz
•
3rd Grade
10 questions
PERSONAL PRONOUNS
Quiz
•
3rd Grade - University
15 questions
Homophones
Quiz
•
3rd Grade