10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
1. …………..is responsible to design and construct structures and buildings for the employees during the construction phase
a. The contractor
b. The consultant
c. The owner
d. The client
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
2. What is the minimum clear spacing between non-combustible buildings larger than 548 m2 and/or between clusters of smaller buildings totaling more than 548 m2 ?
a. 6.1 m
b. 3 m
c. 2 m
d. 10 m
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
3. …………is the minimum clear spacing from perimeter fences to buildings
a. 3 m
b. 5 m
c. 1 m
d. 1.8 m
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
4. ……………. is The minimum clear spacing between smaller buildings and buildings within a cluster
a. 3 m
b. 5 m
c. 1.8 m
d. 10 m
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
5. Which of the following areas is suitable in Camp accommodation rooms per occupant?
a. Not less than 4.6 m2
b. Not less than 8 m2
c. Not less than 2 m2
d. Not less than 10 m2
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
6. For the pre-engineered modular buildings, ………. is the minimum wall thickness
a. 2 inches
b. 4 inches
c. 6 inches
d. 8 inches
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
7. ………………..is responsible to provide the welfare facilities in the camp?
a. The contractor
b. The consultant
c. The owner
d. The client
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?