PMI ACP: Domain V  - Adaptive Planning

PMI ACP: Domain V - Adaptive Planning

Professional Development

28 Qs

quiz-placeholder

Similar activities

FORGCF5

FORGCF5

Professional Development

27 Qs

Yoosh Personal Skills Quiz

Yoosh Personal Skills Quiz

Professional Development

23 Qs

bspk

bspk

Professional Development

30 Qs

Chapter 1 Exam

Chapter 1 Exam

Professional Development

23 Qs

PBU - Developer Sales - Test - Jul 2022

PBU - Developer Sales - Test - Jul 2022

Professional Development

24 Qs

Networking

Networking

Professional Development

25 Qs

Retreat - Gallery Walk

Retreat - Gallery Walk

Professional Development

23 Qs

Project Management Quiz Cost

Project Management Quiz Cost

Professional Development

23 Qs

PMI ACP: Domain V  - Adaptive Planning

PMI ACP: Domain V - Adaptive Planning

Assessment

Quiz

Other

Professional Development

Hard

Created by

Stella Stella

Used 3+ times

FREE Resource

28 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile project manager has contracted with another party to develop some of the work required for the project. The external contractor is also using agile project management. How should the progress of the contractor be assessed?

Review the weekly progress reports from the contractor

Review the contractor's release plans and attending the contractors daily stand up meetings

Review the contractor's iteration plans

Review release versions of the work

Answer explanation

Correct. The seventh guiding principles of the agile manifesto indicates "working software is the primary measur of the progress".

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A team has several costly risks which may soon arise on a project. What is the best way for the team to communicate these risks so they can be addresses as impediments to progress?

Daily stand up meetings

Burndown charts

Risk registers

Risk Management Plan

Answer explanation

Correct. During the daily standup meeting, each team member identifies obstacles that impede their work. These obstacles can include risks, and mentioning them in the daily meeting communicates that a risk has occured and becoma an issue, an impediment that need attention.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile team is using rolling wave planning and progressive elaboration to plan work on their new project. Which of the following choices aligns with this method of planning?

Building wireframes and prototypes

Planning at multiple levels

Creating a work breakdown strucure

Reviewing product increments

Answer explanation

Correct. By planning at multiple levels (release, iteration, day), agile teams implement the concepts of the rolling wave planning and progressive elaboration approach to plan their work on upcoming projects.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile team wants to use a quick method using relative size to estimate the user stories. Which metric should they use?

Ideal time

Real time

Velocity

Story Points

Answer explanation

Correct. a story point is an arbitrary measure used by scrum team. It is used to measure the effort required to implement a story (a number that tells the team how difficult the story is). A story point value is defined on a relative range o values.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Before starting actual development of a new software system, an agile team is testing different technical approaches to understand the viability of their potential solutions. What are the team members doing?

Software spike

System spike

Architectural spike

Technical spike

Answer explanation

Correct. There are 2 types of spikes: architectural and risk-based. Architectural spikes are used to test different technical approached and understand the viability of potential solutions before starting the actual development.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile team meets to create the initial release plan for the project. Which of the following is the lowest level of detail considered when developing a release plan?

Tasks

Products

Iterations

User stories

Answer explanation

Correct. The lowest level of detail during release planning is the features or capabilities the stakeholders want to be included in the release, which described in user stories.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a recent iteration, an agile team completed 15 user stories out of 20 planned. The project stakeholders were unhappy and demanded answers. The team members responded that they had to do the routine work of supporting prior releases which caused them to miss the iteration goal. Should the routine work of supporting prior releases be included in the iteration?

No, routine work of supporting prior releases should not be included in the iteration

Yes, routine work of supporting prior releases should be included in the iteration

Yes, routine work of supporting prior releases should be included, but only in iteration Zero

It depends on how many user stories have to be removed by including the work of supporting prior releases.

Answer explanation

Correct. Routine work of supporting prior releases should be included as part of any iteration.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?