An agile project manager has contracted with another party to develop some of the work required for the project. The external contractor is also using agile project management. How should the progress of the contractor be assessed?

PMI ACP: Domain V - Adaptive Planning

Quiz
•
Other
•
Professional Development
•
Hard
Stella Stella
Used 3+ times
FREE Resource
28 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Review the weekly progress reports from the contractor
Review the contractor's release plans and attending the contractors daily stand up meetings
Review the contractor's iteration plans
Review release versions of the work
Answer explanation
Correct. The seventh guiding principles of the agile manifesto indicates "working software is the primary measur of the progress".
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A team has several costly risks which may soon arise on a project. What is the best way for the team to communicate these risks so they can be addresses as impediments to progress?
Daily stand up meetings
Burndown charts
Risk registers
Risk Management Plan
Answer explanation
Correct. During the daily standup meeting, each team member identifies obstacles that impede their work. These obstacles can include risks, and mentioning them in the daily meeting communicates that a risk has occured and becoma an issue, an impediment that need attention.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team is using rolling wave planning and progressive elaboration to plan work on their new project. Which of the following choices aligns with this method of planning?
Building wireframes and prototypes
Planning at multiple levels
Creating a work breakdown strucure
Reviewing product increments
Answer explanation
Correct. By planning at multiple levels (release, iteration, day), agile teams implement the concepts of the rolling wave planning and progressive elaboration approach to plan their work on upcoming projects.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team wants to use a quick method using relative size to estimate the user stories. Which metric should they use?
Ideal time
Real time
Velocity
Story Points
Answer explanation
Correct. a story point is an arbitrary measure used by scrum team. It is used to measure the effort required to implement a story (a number that tells the team how difficult the story is). A story point value is defined on a relative range o values.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Before starting actual development of a new software system, an agile team is testing different technical approaches to understand the viability of their potential solutions. What are the team members doing?
Software spike
System spike
Architectural spike
Technical spike
Answer explanation
Correct. There are 2 types of spikes: architectural and risk-based. Architectural spikes are used to test different technical approached and understand the viability of potential solutions before starting the actual development.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team meets to create the initial release plan for the project. Which of the following is the lowest level of detail considered when developing a release plan?
Tasks
Products
Iterations
User stories
Answer explanation
Correct. The lowest level of detail during release planning is the features or capabilities the stakeholders want to be included in the release, which described in user stories.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a recent iteration, an agile team completed 15 user stories out of 20 planned. The project stakeholders were unhappy and demanded answers. The team members responded that they had to do the routine work of supporting prior releases which caused them to miss the iteration goal. Should the routine work of supporting prior releases be included in the iteration?
No, routine work of supporting prior releases should not be included in the iteration
Yes, routine work of supporting prior releases should be included in the iteration
Yes, routine work of supporting prior releases should be included, but only in iteration Zero
It depends on how many user stories have to be removed by including the work of supporting prior releases.
Answer explanation
Correct. Routine work of supporting prior releases should be included as part of any iteration.
Create a free account and access millions of resources
Similar Resources on Quizizz
23 questions
Global HRM Quiz

Quiz
•
Professional Development
23 questions
Video games

Quiz
•
1st Grade - Professio...
25 questions
Bukber Trivia Games

Quiz
•
Professional Development
30 questions
bspk

Quiz
•
Professional Development
30 questions
Atoha PMP lesson 9

Quiz
•
Professional Development
24 questions
basket ball nba

Quiz
•
KG - Professional Dev...
30 questions
PMP PMBOK Module 1-4 Self Assessment

Quiz
•
Professional Development
27 questions
Security + (SY0-501) Domain 4

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade