PMP BE Batch 17

PMP BE Batch 17

Professional Development

15 Qs

quiz-placeholder

Similar activities

Applied Project Management

Applied Project Management

Professional Development

20 Qs

SCRUM

SCRUM

University - Professional Development

10 Qs

Introduction to Management

Introduction to Management

University - Professional Development

10 Qs

SAFe for Teams - Lesson 2

SAFe for Teams - Lesson 2

Professional Development

14 Qs

Am I a leader or a manager?

Am I a leader or a manager?

Professional Development

15 Qs

BIMT

BIMT

Professional Development

15 Qs

Quick Revision: Managers & Management

Quick Revision: Managers & Management

University - Professional Development

10 Qs

7 Styles of Leadership

7 Styles of Leadership

Professional Development

15 Qs

PMP BE Batch 17

PMP BE Batch 17

Assessment

Quiz

Education

Professional Development

Hard

Created by

pmp be

Used 2+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1.  Due to an uncertain market environment and complexity of upcoming projects, your company is considering a transition from a traditional (predictive/waterfall) to hybrid (agile & predictive) project management approach. The company tasks you with researching various options for incorporating new project management practices that would help the company move closer to its goal. Which of the following would you least likely recommend?

Involving business analysts in requirements management

b. Increasing the level of detail during initial project planning

c. Implementing tools to identify complex project elements

d. Incorporating agile, incremental (predictive, and iterative practices

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2.      The first phase of your project has come to an end. What is the most important thing to ensure is done before beginning the next phase?

A.     Verify that the resources are available for the next phase

B.     Check the project’s progress compared to its baselines

C.     Confirm that the phase has reached it objectives and have its delivery formally accepted

D. Recommend corrective action to bring the project results in line with project

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

3.      You are using a burn up chart to visually provide information about project progress to the agile team. Which of the following are NOT TRUE regarding a burn up chart?

A.     This is a type of capacity measure.

B.     This shows remaining work effort for the iteration or project.

C. Accuracy depends on the accuracy of the team's estimates

D.     It can't tell you if you are working on the right things.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

4.      You are leading a software development project for a client. Due to unstable requirements, you have elected to use a change-driven life cycle. You are currently facilitating an iteration planning meeting with the product owner and the development team. What should you do as part of the meeting?

A.      Control the scope to prevent scope creep

B.      Review the product increment and get feedback

C.      Make sure the scope of the iteration is fixed

D.      Recommend improvements for the next iteration

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

  1. 5. A team member comes to the Project Manager during project executing because he has not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of Work packages?

A. WBS dictionary

B.     Project scope statement

C.     Activity List

D. Scope Management Plan

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

  1. 6. During project execution, the sponsor informs the project manager that a new influential stakeholder has just joined the organization and will be responsible for a few aspects of the project. What is the best course of action for the project manager to learn about the stakeholder's requirements and expectations?

A.   Revise the stakeholder engagement assessment matrix

B.   Submit a change request to update the stakeholder engagement pla

C.   Update the RACI chart with the responsibilities of the new stakeholder

D.   Schedule a meeting with the new project stakeholder

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7.      You are using a burn up chart to visually provide information about project progress to the agile team. Which of the following are NOT TRUE regarding a burn up chart?

A.     This is a type of capacity measure.

B.     This shows remaining work effort for the iteration or project.

C. Accuracy depends on the accuracy of the team's estimates

D.     It can't tell you if you are working on the right things.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?