10A PMI - 2

10A PMI - 2

Professional Development

50 Qs

quiz-placeholder

Similar activities

Present Perfect Progressive Tense

Present Perfect Progressive Tense

Professional Development

48 Qs

Reduced Adjective Clauses Quiz 1

Reduced Adjective Clauses Quiz 1

Professional Development

55 Qs

VOCA - TEST 1 - VOL 1

VOCA - TEST 1 - VOL 1

4th Grade - Professional Development

45 Qs

Preps 250-300

Preps 250-300

5th Grade - Professional Development

50 Qs

C1 U3 & U4 REVIEW

C1 U3 & U4 REVIEW

Professional Development

49 Qs

ETS 2022 - RC 7- VOC 31

ETS 2022 - RC 7- VOC 31

Professional Development

45 Qs

Reporting verbs

Reporting verbs

Professional Development

48 Qs

Software Engineering Quiz

Software Engineering Quiz

Professional Development

45 Qs

10A PMI - 2

10A PMI - 2

Assessment

Quiz

English

Professional Development

Hard

Created by

Chris Nguyen

Used 1+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Due to regulatory changes, a government agency is now a key stakeholder on a complex project. The project manager wants to develop an understanding of this new project stakeholder and any new high-level risks. What should the project manager use?
Meetings
Assumption log
Stakeholder engagement plan
Benefits management plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is ready to close a project. What should the project manager do next?
Resolve all project risks to ensure that the deliverables will be accepted.
Manage quality to validate that the deliverables have met standards.
Measure the project deliverables against the project charter and request customer acceptance.
Review the project management plan to ensure the scope's completion and request customer acceptance.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project is completed, and closeout activities are underway. The project manager discovers that a team member is performing operations activities unrelated to the project scope, but necessary for regular operations. Since the final deliverables must be handed over to operations, what should the project manager do?
Train a resource from operations to perform the activities.
Issue a change request and obtain approval from the change control board (CCB).
Temporarily transfer the team member to operations.
Ask the team to assist in completing the operations work and close the project.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has ended; however the project manager and project team members are still called to solve technical issues, make some small changes, and evaluate new requirements. What should the project manager do to guarantee the product or service developed by the project now has operational support?
Obtain project acceptance.
Perform a project handoff.
Disband the project team and find a new project.
Fulfill all remaining needs as the product is still under development.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager learns that a new law, which will affect the business' type of products, is expected to be passed within the next three to six months. A project to launch a new product is being initiated, and is expected to be complete within two-and-half months. This new product would not meet the requirements of the proposed legislation if it passes. What should the project manager do?
Meet with the sponsor and key stakeholders to discuss the risks, then update the assumption log and project charter based on the results of that meeting.
Advise the project sponsor and stakeholders to cancel the project until the legislation comes into effect.
Ensure that the product is completed without any delays so that it is unaffected by the potential change in legislation.
Continue to plan the project, but update the risk management plan.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a demo and review meeting, the progress report shows that an agile project is not on track. The project manager is surprised, because all work was purposely selected and sequenced to meet higher-level objectives. What should the project manager have done to prevent this miscommunication?
Trained and mentored the team on using the agile approach
Engaged the team to record the agile progress reporting system
Created a contingency reserve
Encouraged the team to self-organize and provide buy-in to the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Due to scope changes during project execution, the project manager identifies that a provider must make changes to a product module already in use. What should the project manager do first?
Check the procurement management plan and the contract terms.
Update the risk register and issue log with this information.
Negotiate directly with the provider to reach an agreement
Prepare a change request to update contract terms with the provider.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?