Select three ways in which Scrum Master supports the Product Owner.
Scrum Master Certification PSM 1 Prep

Quiz
•
Specialty
•
Professional Development
•
Easy
AgilePro School
Used 14+ times
FREE Resource
80 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Assigning the work to Developers when the Product Owner is unavailable
Facilitating Scrum events as requested or needed
Finding techniques for effective Product Backlog management
Helping the Scrum Team understand the need for clear and concise Product Backlog items
Meeting stakeholders face to face and gather requirements
Answer explanation
The Scrum Master serves the Product Owner in several ways, including Helping find techniques for effective Product Goal definition and Product Backlog management; Helping the Scrum Team understand the need for clear and concise Product Backlog items; Helping establish empirical product planning for a complex environment; and, Facilitating stakeholder collaboration as requested or needed. Product Owner meets the stakeholders to gather requirements. No one assigns work to Developers.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While estimating Product Backlog items, a team member says it takes 2 days to perform a task whereas the other person says 6 days, while the rest of the team says 4 days. How should the team proceed?
Choose the shortest estimate
Discuss the variances and reestimate until consensus is reached
Ask the Product Owner to decide on the estimate
Choose the longest estimate
Answer explanation
It is common for team members to estimate differently. That's when they have to discuss the reasoning behind their estimate and reach a consensus.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which is NOT the responsibility of a self-managing Team?
Create an Increment by the end of the Sprint
Raise impediments to the Scrum Master
Send daily status reports to the Product Owner
Update the Sprint Backlog
Answer explanation
A self-managing Team works independently by pulling the work from Product Backlog, assigning the work within the team, track progress, update Sprint Backlog regularly and raise impediments to the Scrum Master.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Product Owner is on leave when Sprint Review is scheduled, but he already had an informal meeting with the team and accepts the increment. Developers ask the Scrum Master to lead the meeting. What should he/she do?
Cancel the Sprint Review meeting as the work is already accepted by the Product Owner
Cancel the Sprint Review meeting because Product Owner is unavailable
Agree with the team and present the increment to the stakeholders in the Sprint Review
Encourage the team to lead the meeting and present the increment
Answer explanation
Cancelling any Scrum event is unacceptable. Developers are a better choice to present the increment to the stakeholders. Scrum Master can still support the team by ensuring that the meeting is going as planned.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Team with 8 members is struggling to finish Daily Scrum in 15 minutes. What should the Scrum Master do?
Allow only senior members to attend the Daily Scrum
Coach the team on how to conduct the meeting within 15 minutes
Conduct 2 Daily Scrums in parallel with 4 members in each meeting
Extend the Daily Scrum to 30 minutes
Answer explanation
Daily Scrum is a Developers' event and Scrum Master need not be present. But if the team is struggling to complete the event within the time box, Scrum Master coaches the Developers. He can teach them time management techniques and also attend a few Daily Scrum meetings to help them through.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the Sprint, the Developers realize that they need the expertise of DBA to complete a valuable feature. As a Scrum Master, what should you do?
You ask the Developers to stop working on the feature and move it to next Sprint
You forbid them from getting external help because Developers are supposed to be cross-functional
Add a DBA to the Scrum Team
You help the team to get the support for a DBA who is external to the project. However, you recommend the team members to develop their skills in that area for the future Sprints
Answer explanation
Since the team is working on a very valuable feature, it is not recommended to move the work to next Sprint. As a Scrum Master, you can help them by getting external help but reminding the team that they must have all the skills required to turn the Product Backlog items into a shippable increment.
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Select two activities Developers perform during the Sprint.
Report the status to Product Owner
To work with Product Owner when clarifications are required
Send the status reports to stakeholders
To develop an increment
Answer explanation
Developers develop a product increment during a Sprint and also works with Product Owner when they need clarifications.
Create a free account and access millions of resources
Similar Resources on Quizizz
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade