1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
IPM - Chapter 7 (Cost Management)
Quiz
•
Education
•
University
•
Medium
Nguyen Thi Vu Ha
Used 7+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
A. Definitive estimate
B. Rough order of magnitude estimate
C. Wide Estimate
D. Plan Estimate
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is Cost Variance (CV)?
350
- 75
400
-50
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager working on a project that requires 100 items to be tested, spaced evenly over five weeks. you have just begun week three, with an overall budget of $10,000 to date, you have spent $2,000 with 40 items tested successfully. What does the cost variance (CV) tell you in this circumstance?
The project is proceeding at 100% of the expected rate.
The project is $2000 under budget.
The project is on budget.
The project is getting $2 of work for every dollar spent.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is $200,000 and that of Activity B is $100,000. The planned value of these activities are $180,000 and $80,000 respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.
0.7
0.8
0.9
0.6
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The estimate at completion (EAC) is typically based on:
The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.
The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).
The earned value (EV) and the actual cost for work completed (AC).
The cost performance index (CPI) and the cost variance (CV).
10 questions
Topic 1- Introduction to estimating
Quiz
•
University
15 questions
Mövzu 2 -Maliyyə sistemi
Quiz
•
University
10 questions
Guidance and Counselling
Quiz
•
University
15 questions
C05 : INDUSTRIAL AUTOMATION SYSTEMS PROJECT COORDINATION
Quiz
•
University
16 questions
Cost Estimating Theory
Quiz
•
12th Grade - University
10 questions
Globalization of Electric Vehicles Quiz
Quiz
•
University
10 questions
All About GPA
Quiz
•
University
12 questions
Semester-long Quiz
Quiz
•
University
25 questions
Equations of Circles
Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)
Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System
Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice
Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers
Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons
Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)
Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review
Quiz
•
10th Grade