IPM - Chapter 7 (Cost Management)
Quiz
•
Education
•
University
•
Medium
Nguyen Thi Vu Ha
Used 7+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
A. Definitive estimate
B. Rough order of magnitude estimate
C. Wide Estimate
D. Plan Estimate
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is Cost Variance (CV)?
350
- 75
400
-50
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager working on a project that requires 100 items to be tested, spaced evenly over five weeks. you have just begun week three, with an overall budget of $10,000 to date, you have spent $2,000 with 40 items tested successfully. What does the cost variance (CV) tell you in this circumstance?
The project is proceeding at 100% of the expected rate.
The project is $2000 under budget.
The project is on budget.
The project is getting $2 of work for every dollar spent.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is $200,000 and that of Activity B is $100,000. The planned value of these activities are $180,000 and $80,000 respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.
0.7
0.8
0.9
0.6
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The estimate at completion (EAC) is typically based on:
The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.
The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).
The earned value (EV) and the actual cost for work completed (AC).
The cost performance index (CPI) and the cost variance (CV).
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple

Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
15 questions
Punjab GK
Quiz
•
1st Grade - Professio...
10 questions
First_Year_Orientation
Quiz
•
University
10 questions
Sharing Schoolarship
Quiz
•
University
15 questions
AISAT History, Mission, Vision and Hymn
Quiz
•
University
9 questions
Animals
Quiz
•
KG - Professional Dev...
15 questions
Tipos de investigación
Quiz
•
University
15 questions
Classical Sociological Approaches to Education
Quiz
•
University
14 questions
Interpersonal Communication Quiz
Quiz
•
12th Grade - University
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade
Discover more resources for Education
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
36 questions
Unit 5 Key Terms
Quiz
•
11th Grade - University
38 questions
Unit 6 Key Terms
Quiz
•
11th Grade - University
20 questions
La Hora
Quiz
•
9th Grade - University
7 questions
Cell Transport
Interactive video
•
11th Grade - University
7 questions
What Is Narrative Writing?
Interactive video
•
4th Grade - University